The words on your contract,
in plain English.
94 terms used on UK construction projects, defined as they are actually used, with a link to the page that treats each one properly.

Getting paid.
The statutory payment regime, and the documents that decide whether a sum is due.
Application for payment
A subcontractor's formal request for payment for work done in a valuation period, setting out the sum claimed and how it is calculated. Where the contract provides for it, an application can also stand as the payment notice, which makes the sum in it the notified sum the payer must actively displace.
It is not an invoice and not a chase. It is the document that starts the statutory payment timetable.
Due date
The date a payment becomes due under a construction contract. Every construction contract must provide an adequate mechanism for determining it, and the payment notice and final date for payment are both measured from it.
Under the Scheme for Construction Contracts the default is seven days after the end of the relevant period, or the date the claim is made, whichever is later.
Payment notice
The notice given by the payer, not later than five days after the due date, stating the sum it considers due and the basis on which that sum is calculated. It is what fixes the notified sum for that payment cycle.
If the payer fails to give one, section 110B allows the payee to serve a default payment notice instead.
Pay less notices and the timetableFree payment notice template
Notified sum
The sum stated in whichever payment notice validly stands for a payment cycle. Section 111 of the Construction Act requires the payer to pay the notified sum in full on or before the final date for payment, unless it has served a valid pay less notice.
Pay less notice
The payer's written notice that it intends to pay less than the notified sum. It must specify the sum the payer considers due at the date of the notice and the basis on which that sum is calculated, and it must be served before the final date for payment by the period the contract prescribes.
The Scheme's default is not later than seven days before the final date for payment. Served late, it is not a weak notice: it is not a notice at all.
Pay less notices and the timetableFree pay less notice template
Final date for payment
The date by which the money must actually be paid. It is distinct from the due date, which only starts the clock, and the Scheme's default is seventeen days after the due date.
Smash and grab
An adjudication brought on the basis that no valid payment notice or pay less notice was served, so the notified sum is payable in full regardless of what the work was worth. It asks nothing about value.
The payer can generally then start a separate true value adjudication, so it is usually a timing and cash flow advantage rather than a permanent one.
Pay when paid
A contract term making payment conditional on the payer first receiving payment from someone else. Section 113 of the Construction Act makes such terms ineffective, with one exception: where that third party is insolvent.
Retention
A percentage deducted from every interim valuation and held by the paying party as security against defects. Commonly three or five per cent on subcontracts, usually capped, and released in two halves.
It is not held in trust unless the contract says so, which most do not. That makes it working capital in somebody else's business.
Defects liability period
The period after practical completion during which the contractor remains liable to return and rectify defects. Commonly twelve months, sometimes six on short works and up to twenty-four on mechanical and electrical packages.
Its end date governs the second half of retention, which is the half firms most often fail to collect. Also called the rectification period.
Making good certificate
The document confirming that defects notified during the defects liability period have been rectified. On many contracts the second half of retention falls due on this certificate rather than simply at the end of the period.
If nobody asks for the certificate, the money never becomes due, and it is not late in any contractual sense.
Final account
The agreed statement of the total sum payable for the works, settling the original contract sum together with variations, remeasurement, claims and adjustments.
Retention sits behind it, so a final account that drifts takes the retention with it.
Default payment notice
A notice given by the payee under section 110B where the payer has failed to give its own payment notice. The sum stated in it becomes the notified sum, and the final date for payment is postponed by the same number of days as the delay.
Where the contract provides for the payee to make an application, a properly made application can serve this purpose. It is the most under-used right in the payment regime.
True value adjudication
An adjudication deciding what the work was actually worth, as distinct from what the notices made payable. A payer that has paid a notified sum it disputes can bring one to recover an overpayment.
The payer generally has to pay the notified sum first rather than raising valuation as a defence, which is where the commercial value of a smash and grab comes from.
Statutory interest
Interest chargeable on a late commercial debt under the Late Payment of Commercial Debts (Interest) Act 1998, at eight percentage points above the Bank of England base rate, as simple rather than compound interest.
A fixed compensation sum is due in addition, of £40, £70 or £100 depending on the size of the debt, plus reasonable recovery costs above that.
Contracts and claims.
The statutory framework, and the mechanisms that resolve a dispute without going to court.
The Construction Act
The Housing Grants, Construction and Regeneration Act 1996, as amended by the Local Democracy, Economic Development and Construction Act 2009. It gives parties to a construction contract a statutory payment timetable and the right to adjudicate at any time.
Contracts with a residential occupier are excluded by section 106. Since 1 October 2011 it applies to contracts that are not in writing.
The Scheme for Construction Contracts
The statutory default terms that apply where a construction contract fails to provide compliant payment or adjudication provisions. It fills gaps rather than overriding a contract that already complies.
England and Wales, Scotland and Northern Ireland each have their own version, so an English default period cannot be lifted onto a Scottish job.
Adjudication
A statutory dispute procedure available to any party to a construction contract at any time. The adjudicator must reach a decision within twenty-eight days of referral, and that decision binds the parties until the dispute is finally determined by court, arbitration or agreement.
The period can be extended by fourteen days with the referring party's consent, or longer if both sides agree after referral. Parties generally cannot recover their own legal costs.
Suspension for non-payment
The right under section 112 of the Construction Act to suspend performance of any or all obligations where the notified sum has not been paid by the final date for payment, after giving at least seven days' written notice.
It carries an entitlement to reasonable costs and expenses and to time for the delay. Leaving site without serving the notice forfeits both.
When the contractor above you will not payFree notice of intention to suspend
Variation
A change to the scope of the works instructed after the contract was formed, valued and added to or deducted from the contract sum.
The recurring problem is not entitlement but evidence: a verbal instruction is still an instruction, but it has to be capable of being proved.
Dayworks
Work valued on the basis of the labour, plant and materials actually used, rather than against a contract rate, usually where no applicable rate exists.
Dayworks sheets signed on site at the time are among the most useful records a subcontractor can hold.
Practical completion
The point at which the works are complete enough for the employer to take possession and use them, notwithstanding minor outstanding items. It triggers the start of the defects liability period and the first release of retention.
On a subcontract it matters greatly whether release turns on your practical completion or the main contract's.
Liquidated damages
A sum stated in the contract as payable for each period of delay beyond the completion date, agreed in advance so neither party has to prove actual loss.
Condition precedent
A contractual requirement that must be satisfied before an entitlement arises, most often a notice given within a stated period. Miss the window and an otherwise good claim can be barred entirely.
This is one of the few places in construction where the paperwork genuinely is the whole thing, so it is worth knowing which of your contract clauses are drafted this way.
Extension of time
Additional time granted for completion where a delay is caused by an event the contract puts at the employer's risk. It protects against liquidated damages and is a separate entitlement from any money claim.
Time and money are claimed separately. Firms routinely secure one and forget the other.
Contemporaneous records
Records created at the time the events happened rather than reconstructed later: site diaries written daily, dayworks signed on the day, dated photographs. They are the evidence almost every construction claim turns on.
A diary written up on Friday for the whole week is worth considerably less than one written each day, and both sides know it.
Tax and CIS.
The two schemes that take a slice of a construction invoice before it reaches you.
Construction Industry Scheme (CIS)
The HMRC scheme under which a contractor deducts tax at source from payments to subcontractors and pays it to HMRC on their behalf. The deduction is a payment on account of the subcontractor's eventual tax, not a charge.
Rates are 20% for registered subcontractors, 30% for unregistered or unverified, and 0% with gross payment status.
The CIS deductions guideWhat counts as construction work under CIS
Gross payment status
CIS registration that allows a subcontractor to be paid without any deduction at source, so it receives the full value of its invoices and settles its tax in the ordinary way.
It has business, turnover and compliance tests to meet and an ongoing compliance record to keep. For a labour-heavy firm it is the single largest cash flow improvement available.
CIS deductions suffered
The amounts deducted from a subcontractor's own payments under CIS. A limited company recovers them by reporting them on its Employer Payment Summary, which offsets them against its PAYE and related liabilities.
There is no in-year route to Corporation Tax. Only after the tax year ends can an unrecovered balance be set against it or repaid.
Employer Payment Summary (EPS)
A payroll submission made to HMRC through Real Time Information, used among other things to report CIS deductions suffered so they can be offset against PAYE, National Insurance and student loan liabilities.
An EPS filed without the CIS figures is the most common single reason a construction company is carrying a large balance with HMRC.
VAT domestic reverse charge
The rule, in force since 1 March 2021, under which the customer rather than the supplier accounts for VAT on most construction services between VAT registered businesses where the payment is reported under CIS. The supplier invoices without adding VAT.
It is the default where the conditions are met. A written end user statement switches it off; nothing switches it on.
End user
A business, or group of businesses, that is VAT and CIS registered but does not make onward supplies of the construction services it receives. Supplies to an end user fall outside the VAT reverse charge.
Only once the end user has told the supplier in writing. A verbal assurance changes nothing.
Intermediary supplier
A VAT and CIS registered business connected or linked to an end user, which buys construction services and resupplies them to that end user. Supplies to an intermediary supplier fall outside the reverse charge on the same written notification basis.
CIS verification
Checking a subcontractor with HMRC before paying them, which returns the rate the contractor must deduct at: 20% for those registered under CIS, 30% for those who cannot be verified, and nil for those with gross payment status.
Deducting at the wrong rate is the contractor's problem rather than the subcontractor's, so verification belongs at onboarding.
Payment and deduction statement
The statement a contractor must give a subcontractor showing the payment made and the CIS deduction taken from it. It is the evidence a subcontractor needs to recover those deductions.
Firms that file these as they arrive have a straightforward year-end claim. Firms that have to ring round eleven contractors for copies have a long one.
The 5% disregard
A relief allowing the VAT reverse charge to be ignored where reverse charge services are 5% or less of the value of a supply. It is agreed by both parties at the start of the contract on the overall contracted values, not reassessed invoice by invoice.
Estimating and commercial.
The words that decide whether a job made money, and whether anybody knew in time.
Preliminaries
The costs of running a site that are not attributable to any single item of measured work: supervision, welfare, scaffolding, plant standing, temporary services, insurances and the like.
Prelims are the most commonly under-priced part of a tender, because they are the part that is not drawn.
Provisional sum
An allowance included in a contract sum for work that cannot be properly specified when the contract is entered into. It is expended and adjusted when the work is instructed and valued.
Whether it is defined or undefined changes who carries the programme and preliminaries risk.
Remeasurement
Valuing work by measuring what was actually built against contract rates, rather than paying a fixed lump sum.
Star rate
A rate agreed for work that has no applicable rate in the contract, usually built up from first principles and used to value a variation.
Margin and markup
Markup is the percentage added to cost to reach the selling price. Margin is the percentage of the selling price that is profit. They are different numbers: a 20% markup produces a margin of about 16.7%.
Confusing the two is a common and expensive way to price work at less profit than intended.
Committed cost
Cost a project has irrevocably taken on but not yet been invoiced for, such as an issued purchase order or an instructed subcontract package.
A job costing view that shows only invoices received understates the true position, sometimes by a great deal, and always in the wrong direction.
Aged debt
Outstanding invoices or applications grouped by how long they have been unpaid, normally in bands of current, thirty, sixty, ninety and one hundred and twenty plus days.
Prime cost sum
An allowance in a contract for materials or goods to be supplied by a nominated or selected supplier, where the price is not known when the contract is made. Adjusted against the actual cost when it is.
Often shortened to PC sum, and distinct from a provisional sum, which covers work rather than supply.
Cost value reconciliation
The periodic comparison of what a job has cost against what it has earned, to establish whether it is making the margin it was priced at. Usually shortened to CVR.
A CVR that counts only invoices received rather than committed cost understates the position, always in the same direction.
Overhead recovery
The share of a firm's fixed running costs that each job is priced to carry. Work won at a rate that covers direct cost and margin but not overhead loses money at the company level while appearing profitable on the job.
Contra charge
A deduction a main contractor makes from a subcontractor's payment for a cost it says the subcontractor caused, such as damage, cleaning or putting right defective work. Also called a back charge.
Under a construction contract, taking it off the notified sum needs a valid pay less notice served before the final date for payment. Without one, the full sum is still due.
Schedule of rates
A priced list of items of work, each with a unit rate agreed in advance, so work is valued by measuring what was done and applying the rate. Common in maintenance, term and responsive repairs contracts, where the scope is not known at tender.
The same idea prices damage: a damage schedule of rates sets one agreed charge for each kind of damage or part, so every claim is priced the same way.
Expense claim
A request by an employee to be paid back for money spent on the employer's behalf, supported by the receipt. On site it is usually small purchases of materials, fixings and consumables, paid on the worker's own card or in cash.
Recurring invoice
An invoice raised for the same client and the same lines on a fixed frequency, such as monthly or quarterly. Maintenance contracts, service agreements and retainers are usually billed this way.
Payment terms run from the invoice date, so a recurring invoice raised a week late is paid a week late.
Recurring purchase order
A purchase order repeated to the same supplier on a fixed frequency, for goods or services bought on a regular basis, such as welfare cleaning, skip exchanges or gas cylinders.
Document management system
Software that stores, organises and shares a firm's files in one place, usually in folders for each project and for the company as a whole. For a contractor it holds the enquiry documents, quotations, contracts, drawings, photographs, health and safety records and the handover file.
Many systems meter storage by plan. In Unibuild, storage is unlimited, with no cap on space, number of files or file size.
Accounts payable
The money a business owes its suppliers and subcontractors for goods and services received but not yet paid for, and the office function that checks, approves and pays those invoices.
Accounts payable automation takes the manual steps out: invoices read automatically, matched to the order and delivery, routed for approval and paid in a payment run.
Purchase-to-pay
The whole process from somebody asking to buy something to the supplier being paid: requisition, approval, purchase order, delivery, invoice, matching, payment and remittance. Also called P2P or procure-to-pay.
Purchase requisition
An internal request to buy goods or a service, sent to a manager for approval before anything is ordered. Once approved it becomes a purchase order sent to the supplier.
Three-way matching
Checking a supplier invoice against two other documents before it is approved: the purchase order, for the agreed price, and the goods received note, for the quantity that actually arrived. Two-way matching checks the invoice against the order alone.
Approval workflow
The route a request for money takes before it is committed or paid: who approves it, in what order, and under what conditions, such as value, job or budget.
Payment run
A batch of approved supplier invoices paid together on a set day, weekly, fortnightly or monthly, after a named person approves the batch.
Remittance advice and payment runsAccounts payable automation
Remittance advice
A note from a payer to a supplier confirming a payment and listing the invoices and credit notes it covers, with any deductions. It lets the supplier allocate one bank transfer to the right invoices.
There is no general legal requirement to send one in the UK. Under CIS, a contractor who makes a deduction must give a separate payment and deduction statement within 14 days of the end of the tax month.
Supplier onboarding
Setting up a new supplier before the first order: company and VAT details, contacts, bank account, insurance and accreditations, checked and approved by the buying firm.
Health, safety and compliance.
The duties, the documents and the acronyms that decide whether you can be on site at all.
RAMS
A risk assessment and method statement issued together. The assessment identifies the hazards in an activity and the controls that reduce them; the method statement describes the sequence in which the work will be done with those controls built in.
A RAMS that has not been briefed to the people doing the work has been filed rather than implemented.
RAMS on the platformAI RAMS reviewRAMS that hold upFree RAMS templateRAMS templates by trade
Dynamic risk assessment
The ongoing assessment of risk as conditions become apparent or change on the job. The person doing the work looks at what is happening around them, checks whether the existing precautions are still sufficient, and decides what action is needed before carrying on.
It works alongside the written risk assessment and RAMS for the task, and a change worth acting on is a change worth recording.
Awaab's Law
The law that gives social landlords in England fixed timescales to investigate and make safe hazards in their tenants' homes. An emergency hazard is made safe within 24 hours; a significant hazard is investigated within 10 working days and made safe within 5 working days after that.
It has covered damp and mould and every emergency hazard since 27 October 2025. Phase 2, due on 30 November 2026, adds excess cold and heat, falls, fire and explosions, electrical, structural and domestic hygiene hazards. The duty is the landlord's; the repairs contractor is often the first to see the hazard.
Awaab's Law hazard reporting on the platformAwaab's Law for repair contractorsAwaab's Law phase 2 hazardsFree Awaab's Law hazard report form
HHSRS
The Housing Health and Safety Rating System: the way hazards in homes in England are assessed, from damp and mould to excess cold, falls, fire and electrical hazards. Its list of hazards is the one Awaab's Law draws on.
Since 23 June 2026 it has 21 hazards, down from 29, after similar hazards were merged: falls in bathrooms joined falls on the level, and pests, waste, food safety, personal hygiene and sanitation became one domestic hygiene hazard. Its ten bands became three: High, Medium and Low.
The 21 HHSRS hazardsThe hazards an engineer now reportsSoftware for housing repairs contractors
Category 1 hazard
A hazard in a home whose HHSRS score falls in the High band, 1,000 or more. A local authority in England must take enforcement action on a category 1 hazard. A score in the Medium or Low band is a category 2 hazard, which it has a power to act on.
Awaab's Law does not depend on the category: it asks what a reasonable landlord would make safe within 24 hours or 15 working days.
Emergency hazard
Under Awaab's Law, a hazard that a reasonable social landlord, knowing the tenant's circumstances, would make safe within 24 hours. The landlord must investigate it and make the home safe within 24 hours of becoming aware of it.
Every kind of hazard except overcrowding has been covered as an emergency hazard since 27 October 2025. Temporary measures, such as heaters while a boiler is repaired, can make a home safe in time.
Emergency and significant hazards, with examplesReporting hazards from the property
Significant hazard
Under Awaab's Law, a hazard that a reasonable social landlord, knowing the tenant's circumstances, would make safe within 15 working days. It is investigated within 10 working days, and the safety work is completed within 5 working days of the investigation.
Damp and mould have been covered since 27 October 2025. Excess cold and heat, falls, structural collapse, fire and explosions, electrical and domestic hygiene hazards are due to join them on 30 November 2026.
Toolbox talk
A short briefing, usually five or ten minutes, given on site to the people about to do the work, covering one subject at a time. It is a reminder of a control rather than training, and it is recorded on an attendance register signed by those it was delivered to.
A talk given and not recorded is indistinguishable afterwards from one never given, which is the entire reason the register exists.
CDM 2015
The Construction (Design and Management) Regulations 2015, which allocate health and safety duties across the client, designers, the principal designer and the principal contractor on every construction project in Great Britain.
Principal contractor
The contractor appointed under CDM 2015 to plan, manage and monitor the construction phase where a project involves more than one contractor. The duty attaches to the role, not to the size of the firm.
A second contractor arriving on site is enough to engage it, which is how small firms end up holding the duty without noticing.
F10
The notification given to the Health and Safety Executive for a notifiable construction project under CDM 2015.
CSCS card
A card issued under the Construction Skills Certification Scheme recording that the holder has the training and qualifications for their occupation, together with a health and safety test. It is not a legal requirement but most principal contractors require one for site access.
SSIP
Safety Schemes in Procurement, the umbrella body whose member schemes assess a contractor's health and safety arrangements. Its mutual recognition arrangement means an assessment by one member scheme is generally accepted by another.
That mutual recognition is the point: it is what stops a firm being assessed separately for every supply chain it joins.
RIDDOR
The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013, which require certain workplace incidents to be reported to the enforcing authority.
LOLER thorough examination
The periodic examination of lifting equipment required under the Lifting Operations and Lifting Equipment Regulations 1998, carried out by a competent person and recorded in a report.
The report is the thing an inspector asks for, which is why the expiry date matters as much as the examination.
Construction phase plan
The document the principal contractor must prepare before the construction phase begins, setting out how health and safety will be managed on that project. It has to be reviewed and revised as the work changes.
A plan written once and never touched is not a plan, and the monitoring behind it is what most firms cannot evidence.
When you become the principal contractorWhat goes in each CDM document
Health and safety file
The record of information about a structure that anyone carrying out later construction work on it will need to do so safely. Compiled during the project and handed to the client at the end.
Notifiable project
A construction project that must be notified to the Health and Safety Executive on form F10, based on its duration and workforce size. It is a separate question from whether a principal contractor is required.
The two thresholds are constantly conflated. A project can need a principal contractor without being notifiable, and that combination is very common.
Duty holder
Anyone carrying a defined role under CDM 2015: the client, the designer, the principal designer, the contractor or the principal contractor. The duties attach to the role rather than to the size of the organisation.
Gateway 2
The Building Safety Act approval stage that must be passed before construction begins on a higher-risk building. Applications are made to the Building Safety Regulator and work cannot start until it is granted.
Turnaround has improved sharply: a median of 22 weeks at June 2026 against 43 weeks a year earlier. The programme and cash consequences still fall on subcontractors who are not the applicant.
Retrofit and energy efficiency.
The standards, schemes and guarantees behind insulation and retrofit work in occupied homes.
PAS 2035
The specification for retrofitting existing homes to improve their energy efficiency. It sets a whole-house approach with defined roles for assessment, coordination, design, installation and evaluation, and it applies to government-funded domestic retrofit.
The current version is PAS 2035:2023. Ventilation and moisture risk are assessed before any measure is chosen, because a warmer, more airtight home can become a damper one.
PAS 2035 explained, step by stepSoftware for insulation and retrofit installers
PAS 2030
The specification for installing energy efficiency measures in existing homes. Installers are certified against it measure by measure and audited by their certification body.
Certification for loft insulation does not cover cavity wall or internal wall insulation, so competence is held per measure.
Retrofit Coordinator
The person who manages a PAS 2035 retrofit project from assessment to evaluation. The coordinator assesses the risk path, oversees design and installation, and lodges the finished project with TrustMark.
The coordinator lodges from the installer's evidence, so a missing photograph holds up the lodgement and the payment behind it.
The PAS 2035 rolesLodgement tracking in the Retrofit and Insulation module
TrustMark
The government-endorsed quality scheme for work in and around the home. Government-funded energy efficiency work is done by TrustMark registered businesses and lodged on the TrustMark Data Warehouse, where it is checked for compliance.
CIGA guarantee
The 25-year guarantee from the Cavity Insulation Guarantee Agency for cavity wall insulation fitted by a registered installer. It is issued per property after the installation.
The guarantee stays with the house, so buyers' solicitors and surveyors ask for it when the property is sold.
ECO4
The fourth Energy Company Obligation, which requires larger energy suppliers to fund energy efficiency measures in low-income and vulnerable households. Its end date was extended to 31 December 2026.
Each funded measure needs evidence of eligibility as well as evidence of installation, and the claim is paid on both.
Grant scheme eligibility in the Retrofit and Insulation module
Warm Homes: Local Grant
A government grant in England, delivered by local authorities, for energy efficiency upgrades and low-carbon heating. It is aimed at homes with an EPC rating of D to G, usually where household income is £36,000 or less.
Grant scheme eligibility in the Retrofit and Insulation module
EPC
Energy Performance Certificate: a rating of a building's energy efficiency from A to G, valid for ten years and held on a government register. Many grant schemes set eligibility by EPC band.
UPRN
Unique Property Reference Number: the identifier given to every addressable location in Great Britain. It stays the same however the address is written, which makes it the reliable key for a property record.
Plant, assets and site equipment.
The vocabulary of the kit you own, hire and are still being charged for.
Off-hire
Formally ending a plant hire so charges stop. Hire runs until the item is off-hired, not until you finish with it, and the off-hire number or reference is the evidence that it was done.
Kit sitting in a compound on a finished job, still on hire because nobody made the call, is one of the most common preventable losses in contracting.
Asset register
The record of every item a firm owns, with its serial number, value, location and service history. It is what an insurer asks for after a theft, and it has to exist before the theft rather than after.
PPM
Planned preventative maintenance: servicing carried out to a schedule to keep an asset working and compliant, rather than in response to a failure. Usually driven by dates held against each asset.
Plant on hire
Equipment held under a hire agreement rather than owned. It does not belong to you, which matters both for insurance and for what an administrator can and cannot take if the hirer fails.
Damage recharge
Charging the cost of repairing or replacing damaged equipment to the party liable for the damage, usually the client, the main contractor or a subcontractor. It rests on evidence: where and when the damage happened, who had the item and what the repair cost.
