A notice of intention to suspend performance for non-payment, under section 112 of the Housing Grants, Construction and Regeneration Act 1996, as an editable PDF. It states the ground, the unpaid sum, what will stop and from when, with a guidance page on the conditions.
The party in default and the payee, the contract, the date of the notice, the notified sum and the final date for payment that has passed.
That the notified sum was not paid in full by the final date for payment, and no effective pay less notice was given, with the amount unpaid.
All of your obligations or the ones you list, and the date and time suspension begins, at least seven days after the notice.
The costs and expenses of suspending, and time for the suspended period, stated in the notice itself.
The conditions to check before sending it, and an example timeline on the Scheme's periods.
The notified sum has not been paid in full by the final date for payment, and no effective pay less notice was given.
Section 112(1)At least seven days' notice of intention to suspend, stating the ground or grounds.
Section 112(2)Performance of any or all of your obligations under the contract.
Section 112(1)When the party in default pays the sum in full.
Section 112(3)A reasonable amount for costs and expenses reasonably incurred, and the suspended period is disregarded for contractual time limits on the affected work.
Section 112(3A) and (4)Confirm the notified sum, the final date for payment and that no valid pay less notice arrived. Suspending without the right is itself a breach.
In writing, stating the ground, served the way your contract says notices are given. Keep proof of when it arrived.
The right ends the moment the sum is paid in full, so plan the return to site when you plan the suspension.
The sum due at the payment due date and the basis on which it is calculated, as the Act requires, with a guidance page on the timing.
The sum due at the date of the notice, each deduction with its reason, and the basis of calculation, with a guidance page on the timing.
Risk assessment and method statement for one activity: the sequence of work, a five by five risk matrix, PPE, permits, rescue, and a briefing record signed against the revision.
On the platform the application, the due date, the final date for payment and the notices against it are dated records on the job, so the trail is there when a payment is disputed.