Insight · Getting paid

Charging interest on a late payment,
and the sums nobody claims.

Statutory interest runs at eight per cent above base, and a fixed compensation sum sits on top of it that almost nobody asks for. Both are automatic entitlements rather than favours.

Published ·5 min read·Written by Unibuild

Under the Late Payment of Commercial Debts (Interest) Act 1998 you can charge statutory interest at eight per cent above the Bank of England base rate on a late commercial debt, as simple interest. On top of that, a fixed compensation sum is due per debt: £40 under £1,000, £70 from £1,000 to under £10,000, and £100 at £10,000 or more. Reasonable recovery costs above that fixed sum are also recoverable.

Three entitlements, not one

Almost every page on this subject covers the interest and stops. There are three, they stack, and the second and third are the ones firms leave on the table.

  1. Statutory interest. Eight per cent above the Bank of England base rate, running from the day the payment became late until it is paid. It is simple interest, so it does not compound.
  2. A fixed sum per debt. Once statutory interest starts to run, section 5A entitles you to a fixed sum in addition: £40 where the debt is under £1,000, £70 where it is £1,000 or more but under £10,000, and £100 where it is £10,000 or more. Per debt, which on a firm with many late invoices adds up faster than the interest does.
  3. Reasonable recovery costs above the fixed sum. Where your reasonable costs of recovering the debt exceed the fixed sum, you are entitled to the difference. That is what makes a debt recovery agent's or solicitor's fee recoverable rather than a cost of being owed money.

None of these is a favour you are asking for, and none depends on the contract mentioning them. They are statutory entitlements that apply to commercial debts by default.

The fixed sum is per invoice and it is claimed almost nowhere. On thirty late payments in a year that is a real number sitting unasked for.

Working out the rate

The rate is deliberately not stated as a single figure here, because the base rate moves and any absolute number on a page like this is wrong within months.

What you need is the Bank of England base rate in force at the relevant time, plus eight percentage points. For a commercial contract the rate is fixed by reference to the base rate in force at the end of the six-month period in which the debt became late, and then applies for the following six months, which is why a debt running across a year can have two rates. Look up the base rate for the relevant period rather than using today's.

Then it is arithmetic: debt, multiplied by the rate, divided by 365, multiplied by the number of days late. Simple interest, no compounding.

When it starts running

From the day after payment was due. Where the contract sets a payment period, that governs. Where it does not, the default is 30 days from the later of delivery of the goods or performance of the service, and receipt of the invoice.

Note how that interacts with construction. Your contract almost certainly does set the payment terms, so the relevant date is the contractual final date for payment rather than a generic 30 days. Establish that first, and if you are not sure what it is, the payment timetable calculator works it out.

The limits, honestly

Three things worth knowing before you send an interest schedule to your biggest client.

  • It does not apply to consumers. This is for business to business debts. Work for a homeowner is outside it.
  • A contract can substitute its own remedy, but only within limits: a term that ousts or varies the statutory right is void unless the contract provides a substantial contractual remedy for late payment. It is not enough to simply write the entitlement out.
  • Interest can be remitted where the conduct of the supplier makes it fair, so the provision is not entirely mechanical. In practice this rarely bites on a straightforward unpaid application.

How to actually use it

The commercial reality is that most firms never charge it, because it feels like an escalation with a client they want to keep. That is a fair judgment, and it is worth separating two different uses.

As a claim. On a debt you are already pursuing, add it. If you are at the letter before action stage or beyond, there is no relationship left to protect and the interest plus fixed sums plus recovery costs materially change the number.

As a statement of position. Putting a line on your terms and on the invoice noting that statutory interest and compensation will be applied to overdue amounts costs you nothing and changes how you are treated. Payers triage. A supplier who is visibly aware of the entitlement moves up the run.

The middle path most firms settle on is sensible: state it on every invoice, and claim it selectively.

Where this touches the platform

Claiming this requires two things: knowing which invoices are late and by how many days, and knowing the contractual payment date each was measured against. Unibuild ages outstanding application value into current, thirty, sixty, ninety and one hundred and twenty plus days against the manager responsible, so the population of late payments is a report rather than an exercise. Applications and receipts sit against the project in date order with the total requested, total received, retention held and total outstanding across the top. What it does not do is calculate statutory interest for you or track base rate changes: the figures come from the Act and the Bank of England, and the arithmetic is a spreadsheet job once you have the dates.

Where to start, on Monday

Pull the list of invoices paid more than a fortnight late in the last twelve months and count them. Multiply by the relevant fixed sum band. That number alone, ignoring the interest entirely, is usually enough to make somebody in the business pay attention.

Then add one line to your invoice template and your terms noting the statutory entitlement. It is the cheapest change on this list and the only one that works without you having to do anything afterwards.

Asked most often

The follow-up questions.

Where interest sits in the wider sequence is in when the contractor above you will not pay.

Can I charge interest on a late payment in the UK?+
Yes, on commercial debts. The Late Payment of Commercial Debts (Interest) Act 1998 provides statutory interest at eight per cent above the Bank of England base rate, as simple interest, running from the day after payment was due until it is paid. It applies by default and does not need to be mentioned in the contract. It does not apply to debts owed by consumers.
How much is the late payment compensation fee?+
A fixed sum per debt, due in addition to the interest once statutory interest starts to run: £40 where the debt is less than £1,000, £70 where it is £1,000 or more but less than £10,000, and £100 where it is £10,000 or more. Where your reasonable costs of recovering the debt exceed that fixed sum, you are entitled to the difference as well.
What is the current statutory interest rate for late payment?+
Eight percentage points above the Bank of England base rate. Because the base rate changes, look up the rate in force at the relevant time rather than today's. For a commercial contract the rate is set by reference to the base rate in force at the end of the six-month period in which the debt became late, and applies for the following six months, so a long-running debt can attract two different rates.
When does statutory interest start running?+
From the day after payment was due. Where the contract sets a payment period that governs, which in construction means the contractual final date for payment rather than a generic figure. Where the contract is silent, the default is 30 days from the later of performance of the service and receipt of the invoice.
Can a contract exclude statutory interest on late payment?+
Not simply by writing it out. A term that ousts or varies the statutory right is void unless the contract provides a substantial contractual remedy for late payment in its place. Interest can also be remitted in whole or part where the conduct of the supplier makes it fair to do so, though that rarely bites on a straightforward unpaid application.
Read next

More from Insights.

Getting paid··5 min readAn application for payment that does not come back rejectedFour reasons account for most rejections, and none of them is the price. What the document has to contain, what has to sit behind it, and the date that matters more than the total.Read it Getting paid··5 min readGetting paid for variations you were told to get on withThe entitlement is rarely the problem. The evidence is. What stands up when the instruction was verbal, and the one email that changes the argument.Read it Getting paid··5 min readWhen a missing notice hands you the moneyAn adjudication that asks nothing about what the work was worth, only whether the notices were served. What it wins, and the second adjudication that usually follows it.Read it Getting paid··5 min readStopping work for non-payment, without breaching your contractA statutory right with narrow conditions and real leverage. What has to be true before you can use it, what the notice must say, and what walking off without one costs.Read it Getting paid··6 min readWhat the Construction Act actually gives youSix rights that apply whether or not your contract mentions them, and whether or not anything was ever signed. What each one is, and where it stops.Read it Subcontractors··6 min readVetting a subcontractor before you instruct themNine checks, what each one is actually protecting you from, and the two that firms skip and then discover matter. Most of it is twenty minutes and free.Read it Reducing risk··6 min readCredit checking the firm above you, free, in twenty minutesEverything you need is public and none of it costs anything. Filing history, charges, director record, county court judgments, and the payment data large firms are now compelled to publish, including what they do with retention.Read it Commercial··5 min readQuote or estimate, and which one binds youOne is an offer that becomes a fixed price the moment it is accepted. The other is an informed guess. Almost nobody says which they are sending, and the word at the top of the page is not what decides it.Read it Health and safety··5 min readWhen you become the principal contractor without being toldThe duty attaches to a role, not to the size of the firm, and a second contractor arriving on site is enough to trigger it. What lands on you, and what happens when the client never appointed anybody.Read it Choosing software··6 min readWhat construction software actually costsThe monthly figure is the part everyone compares and the smallest part of the bill. Setup, migration, the annual uplift, and the licences you ration because they are charged per person.Read it Tax and CIS··8 min readThe VAT reverse charge, and who accounts for the VATFive years in and it still catches firms out on every second invoice. When it applies, when it does not, the written statement that switches it off, and the wording your invoice has to carry.Read it Tax and CIS··7 min readReclaiming CIS deductions, and the money sitting with HMRCA limited company gets its deductions back through payroll rather than through its Corporation Tax return, and only if somebody files the right submission every month. Where the money goes, and how to stop it piling up.Read it Commercial··7 min readThe gap between doing the work and having the moneyWages go out weekly, materials at thirty days, and the money comes back at sixty. Retention, CIS and the reverse charge each take a slice on the way. Why a job that made a profit can still run a firm out of cash.Read it Getting paid··8 min readWhen the contractor above you will not payThe remedies run in a fixed order and each one costs more than the last. What to do first, what every step is worth, and the rung most disputes never get past.Read it Getting paid··8 min readPay less notices, and the timetable behind themFour dates govern every interim payment in UK construction, and statute sets them rather than goodwill. What each one is, how to work them out on your own job, and what a late notice costs the party that served it.Read it Getting paid··6 min readPay when paid, and why it does not bind youMaking your money conditional on somebody else being paid has been ineffective in UK construction since 1998. The clause is still written into contracts, still quoted down the phone, and still works on firms that do not know.Read it Site team reviewing a risk assessment and method statement on a UK construction siteHealth and safety··7 min readRAMS that hold upWhat an inspector is actually looking for in a risk assessment and method statement, and the difference between a document that exists and one that is doing its job.Read it Retention and the money that goes missing after practical completionCommercial··6 min readRetention, and the money that goes missing after practical completionWhere cash quietly disappears between the last valuation and the release of the second half of retention, and the four dates that decide whether you ever see it.Read it Why field rollouts stall in week threeImplementation··6 min readWhy field rollouts stall in week threeMost site software is not rejected. It is quietly outlived by the paper route nobody switched off. What the firms that got it to stick did differently.Read it
WhatsApp us, someone is available now