Insight · Getting paid

An application for payment
that does not come back rejected.

Four reasons account for most rejections, and none of them is the price. What the document has to contain, what has to sit behind it, and the date that matters more than the total.

Published ·5 min read·Written by Unibuild

An application for payment states the sum claimed for a valuation period and the basis on which it is calculated, supported by measure, instructions and records. Where the contract provides for it, a properly made application can stand as the payment notice, which makes the sum in it the notified sum the payer has to serve a valid pay less notice to reduce.

It is not an invoice, and the difference is the whole article

An invoice says you owe me this. An application says this is what has been built, here is what it is worth under the contract rates, and here is the evidence.

That distinction has a statutory consequence. Under the Construction Act, the notified sum for a payment cycle is the figure in whichever payment notice validly stands. Normally that is the payer's notice. But where the payer fails to give one, section 110B allows the payee's notice to take its place, and where the contract provides for the payee to make an application, that application can be the notice.

So a well-made application is not a request that somebody may or may not grant. It is the document that sets the number the other side must actively knock down, in writing, before a deadline. A badly made one is a request. The difference costs nothing to close and it is worth a great deal.

Firms rewrite their application every month and never once read the clause that says what an application has to be. That clause is where the money is.

What it has to contain

Six things, and the order matters less than the completeness.

  1. The reference and the period. Application number, the valuation period it covers, and the date it is made. The date drives every subsequent deadline, so it is not administrative.
  2. The sum claimed, and how it was reached. Not a total. The build-up: measured work against contract rates, variations valued separately, materials on site if the contract allows them, less previous payments, less retention. The statutory language is the sum and the basis on which it is calculated, and a total with no basis fails that test.
  3. Measured quantities that somebody can check. Cumulative to date and this period, against the rate. Where the work was quoted through a priced schedule, the application should be measured against those same sections rather than re-described.
  4. Variations, itemised with their instruction reference. Each one separately, with the date and source of the instruction, not folded into a general uplift.
  5. Retention shown, not netted silently. The percentage, the sum this period and the cumulative figure held. A retention figure that only appears as a smaller total is a figure nobody is tracking.
  6. The supporting pack. Signed dayworks, delivery notes, timesheets, site records, photographs where they evidence progress. This is the half most applications are missing and the half that decides whether it is argued.

The four reasons applications come back

In our experience the reasons cluster, and none of them is the price.

  • It was late against the contract dates. An application submitted after the period the contract allows can be treated as belonging to the next cycle, which moves your money a month and hands the payer a clean answer that has nothing to do with your work.
  • The measure is unsupported. A quantity with no record behind it invites a lower quantity from the other side, and the argument is then between two assertions rather than about a document.
  • A variation has no instruction behind it. The commonest single rejection, and the subject of its own article, because the answer is about evidence rather than entitlement.
  • The labour is not evidenced. Hours claimed with no signed record. Where operatives clock in and the record carries a date and a job, this stops being arguable.

The date matters more than the total

Worth stating plainly because it is counter-intuitive: getting the application in on the contractual date, slightly under-claimed, is almost always better than getting it in three days late with a perfect build-up.

A late application starts a later cycle. A slightly light one can be corrected next month. The contract's dates are not a courtesy, and they drive the whole notice timetable that decides whether you get paid in full. If you are not certain what your dates are, the payment timetable calculator works them out, and pay less notices, and the timetable behind them explains why they matter.

Where this touches the platform

This is the document Unibuild produces. Applications are held against the project with their dates, receipts against them, and retention withheld captured against the receipt it came off, so the cumulative figure held is arithmetic rather than archaeology. Where the project was quoted through the platform, the works schedule draws on the priced sections of that quotation with their tendered values, so the measure has a documented origin rather than being retyped from a spreadsheet. Gross applied and gross balance are calculated as at each row's own date rather than only as at today, which is what lets you answer a question about March in November. Hours come from clock-ins with a date and a job attached, which is the evidence behind the labour line. It does not decide what your contract requires an application to contain: read the clause once and set the format to match it.

Where to start, on Monday

Read one clause: the one in your subcontract that says what an application must contain and when it must be made. Then compare it against the application you sent last month, line by line. Most firms find at least one requirement they have never met, and it is usually the basis of calculation.

Then fix the template rather than next month's application, so the improvement applies to every job you have.

Asked most often

The follow-up questions.

The rights behind all of this are in what the Construction Act actually gives you.

What should a construction application for payment include?+
The application reference and valuation period, the date it is made, the sum claimed with the basis on which it is calculated, measured quantities cumulative and for the period against contract rates, variations itemised with their instruction references, retention shown separately, and the supporting pack of dayworks, delivery notes, timesheets and site records. A total with no stated basis fails the statutory test.
What is the difference between an application for payment and an invoice?+
An invoice asserts a debt. An application states what has been built, what it is worth under the contract rates, and what evidences it. The practical difference is statutory: where the contract provides for it and the payer fails to serve its own payment notice, a properly made application can stand as the payment notice, making the sum in it the notified sum the payer must serve a valid pay less notice to reduce.
Why do main contractors reject applications for payment?+
Four reasons account for most of them, and none is the price: the application was late against the contract dates so it falls into the next cycle, the measure has no record behind it, a variation has no instruction behind it, or claimed labour is not evidenced by a signed or timestamped record. All four are document problems rather than commercial ones.
Can my application for payment count as a payment notice?+
Where the contract provides for the payee to make an application, it can. Section 110B allows the payee to give a default payment notice when the payer has failed to give one, and a compliant application can serve that purpose. Whether yours qualifies depends on the contract wording and on how the application is put together, which is exactly why the format is not administrative housekeeping.
Is it better to submit a late application or an under-claimed one?+
Under-claimed, almost always. A late application can be treated as belonging to the next valuation cycle, which moves the whole payment a month and gives the payer an answer that has nothing to do with your work. A slightly light application is corrected in the following period at no cost.
Read next

More from Insights.

Getting paid··5 min readGetting paid for variations you were told to get on withThe entitlement is rarely the problem. The evidence is. What stands up when the instruction was verbal, and the one email that changes the argument.Read it Getting paid··5 min readWhen a missing notice hands you the moneyAn adjudication that asks nothing about what the work was worth, only whether the notices were served. What it wins, and the second adjudication that usually follows it.Read it Getting paid··5 min readStopping work for non-payment, without breaching your contractA statutory right with narrow conditions and real leverage. What has to be true before you can use it, what the notice must say, and what walking off without one costs.Read it Getting paid··5 min readCharging interest on a late payment, and the sums nobody claimsStatutory interest runs at eight per cent above base, and a fixed compensation sum sits on top of it that almost nobody asks for. Both are automatic entitlements rather than favours.Read it Getting paid··6 min readWhat the Construction Act actually gives youSix rights that apply whether or not your contract mentions them, and whether or not anything was ever signed. What each one is, and where it stops.Read it Subcontractors··6 min readVetting a subcontractor before you instruct themNine checks, what each one is actually protecting you from, and the two that firms skip and then discover matter. Most of it is twenty minutes and free.Read it Reducing risk··6 min readCredit checking the firm above you, free, in twenty minutesEverything you need is public and none of it costs anything. Filing history, charges, director record, county court judgments, and the payment data large firms are now compelled to publish, including what they do with retention.Read it Commercial··5 min readQuote or estimate, and which one binds youOne is an offer that becomes a fixed price the moment it is accepted. The other is an informed guess. Almost nobody says which they are sending, and the word at the top of the page is not what decides it.Read it Health and safety··5 min readWhen you become the principal contractor without being toldThe duty attaches to a role, not to the size of the firm, and a second contractor arriving on site is enough to trigger it. What lands on you, and what happens when the client never appointed anybody.Read it Choosing software··6 min readWhat construction software actually costsThe monthly figure is the part everyone compares and the smallest part of the bill. Setup, migration, the annual uplift, and the licences you ration because they are charged per person.Read it Tax and CIS··8 min readThe VAT reverse charge, and who accounts for the VATFive years in and it still catches firms out on every second invoice. When it applies, when it does not, the written statement that switches it off, and the wording your invoice has to carry.Read it Tax and CIS··7 min readReclaiming CIS deductions, and the money sitting with HMRCA limited company gets its deductions back through payroll rather than through its Corporation Tax return, and only if somebody files the right submission every month. Where the money goes, and how to stop it piling up.Read it Commercial··7 min readThe gap between doing the work and having the moneyWages go out weekly, materials at thirty days, and the money comes back at sixty. Retention, CIS and the reverse charge each take a slice on the way. Why a job that made a profit can still run a firm out of cash.Read it Getting paid··8 min readWhen the contractor above you will not payThe remedies run in a fixed order and each one costs more than the last. What to do first, what every step is worth, and the rung most disputes never get past.Read it Getting paid··8 min readPay less notices, and the timetable behind themFour dates govern every interim payment in UK construction, and statute sets them rather than goodwill. What each one is, how to work them out on your own job, and what a late notice costs the party that served it.Read it Getting paid··6 min readPay when paid, and why it does not bind youMaking your money conditional on somebody else being paid has been ineffective in UK construction since 1998. The clause is still written into contracts, still quoted down the phone, and still works on firms that do not know.Read it Site team reviewing a risk assessment and method statement on a UK construction siteHealth and safety··7 min readRAMS that hold upWhat an inspector is actually looking for in a risk assessment and method statement, and the difference between a document that exists and one that is doing its job.Read it Retention and the money that goes missing after practical completionCommercial··6 min readRetention, and the money that goes missing after practical completionWhere cash quietly disappears between the last valuation and the release of the second half of retention, and the four dates that decide whether you ever see it.Read it Why field rollouts stall in week threeImplementation··6 min readWhy field rollouts stall in week threeMost site software is not rejected. It is quietly outlived by the paper route nobody switched off. What the firms that got it to stick did differently.Read it
WhatsApp us, someone is available now