Insight · Getting paid

Pay less notices,
and the timetable behind them.

Four dates govern every interim payment in UK construction, and statute sets them rather than goodwill. What each one is, and what a late notice costs.

Published ·Updated ·8 min read·Written by

A hand writing on documents at a desk

A pay less notice is the paying party's written notice that it intends to pay less than the sum already notified as due. Under the Scheme it has to be served no later than seven days before the final date for payment. Served late, or not served at all, the notified sum falls due in full on that date, whatever the payer believes the work was actually worth.

Why the dates decide more than the valuation does

Most payment arguments in UK construction are conducted as though the question were what the work was worth. Under the statutory payment regime the question is usually narrower, and duller: what sum was notified, and did anybody serve the right notice in time to change it. The valuation matters. It just matters second.

That is deliberate. The Housing Grants, Construction and Regeneration Act 1996, as amended by the Local Democracy, Economic Development and Construction Act 2009, exists to keep money moving down a supply chain that was, and still is, slow. It does that by converting payment into a timetable. Miss a date on that timetable and the Act settles the amount for you, in the other party's favour, without anybody looking at the work.

Which is why this is worth an hour. Firms lose real money on these dates every month, in both directions: main contractors who pay sums they had a perfectly good answer to, and subcontractors who never realised the answer arrived too late to count.

The four dates

Every interim payment runs through the same four points, in the same order.

  1. The due date. The date the payment becomes due. Your contract has to provide an adequate mechanism for working it out, and most do it by reference to a monthly valuation cycle.
  2. The payment notice. Under section 110A the payer, or a person specified in the contract, gives notice not later than five days after the due date, stating the sum considered due and the basis on which it is calculated. This is what fixes the notified sum.
  3. The pay less notice. If the payer intends to pay less than the notified sum, section 111 requires notice before the final date for payment, by whatever period the contract prescribes.
  4. The final date for payment. The date the money has to be with you. Section 111 requires the payer to pay the notified sum, so far as it is unpaid, on or before this date.

Where a contract fails to provide compliant terms, the Scheme for Construction Contracts supplies them. Its default periods are the ones worth memorising, because they are the fallback the whole industry is measured against: the due date is seven days after the end of the relevant period or the date you make your claim, whichever is later; the final date for payment is seventeen days after the due date; and a pay less notice must be given not later than seven days before that final date.

Put real dates on it. Take a valuation period ending on 31 March, with the application made the same day.

The four dates on the Scheme for Construction Contracts default periods, worked through a 31 March valuation
PointScheme default periodOn a 31 March valuation
Due dateSeven days after the end of the relevant period, or the date you make your claim, whichever is later7 April
Payment noticeNot later than five days after the due date12 April
Pay less noticeNot later than seven days before the final date for payment17 April
Final date for paymentSeventeen days after the due date24 April

A pay less notice that turns up on 18 April is a fortnight early in ordinary commercial terms and one day late in statutory ones, and the difference between those two readings is the whole of the sum in dispute.

A pay less notice served one day late is not a weak notice. It is not a notice at all.

If you would rather not count days by hand, the payment timetable calculator takes a valuation date and returns all four, on the Scheme's periods or on your own contract's. It runs in your browser and nothing is sent anywhere.

Read your own contract before you rely on any of that

The Scheme fills gaps. It does not override a contract that already complies, and the standard forms almost all set their own periods. A JCT subcontract and an NEC subcontract each run a different timetable from the Scheme and from one another, and a bespoke amendment can move the dates again.

So the four dates above are the architecture, not the answer. The answer is in your contract, usually in a payment schedule two pages long that nobody has opened since it was signed. The useful exercise is to work the dates out once, for one live job, and write them where the commercial team will see them each month. Most firms discover in the process that they have been treating the application date as the thing that matters, when the date that actually governs is the one seventeen or twenty-eight days after it.

What a pay less notice has to say

Section 111 sets two requirements, and both have to be met. The notice must specify the sum that the payer considers to be due at the date the notice is served, and it must specify the basis on which that sum is calculated.

A figure on its own does not do it. Neither does a general complaint about progress, or an email saying the valuation is under review, or a phone call. The point of the second requirement is that the receiving party has to be able to see how the payer got there, well enough to respond or to refer it. Notices that fail tend to fail on that half rather than the first.

Beyond that, the form is a matter for the contract. An email can be a good notice where the contract permits notices by email and the content is right. A document titled Pay Less Notice can be a bad one where it names a sum and nothing else.

What happens when it is late, or never comes

Section 111 is blunt about it. The payer must pay the notified sum on or before the final date for payment, and the only thing that reduces that obligation is a pay less notice given in time. No valid notice means the notified sum is payable in full, whether or not the work was worth it.

This is the mechanism behind what the industry calls a smash and grab: an adjudication that asks nothing about value and only whether the notices were served. They are short, they are hard to defend, and the sums can be uncomfortable.

Winning on notices is usually a cash flow and timing advantage rather than a permanent windfall. A payer who has paid a notified sum it disputes can generally start its own adjudication on the true value of the work and recover an overpayment. What the notice regime gives you is the money now and the burden of the second fight on them, which in an industry where insolvency runs down the chain is worth a great deal on its own. It is not the same as being right about the valuation.

When the payer serves nothing at all

If the payer misses its own payment notice, you are not stuck. Section 110B lets the payee give a default payment notice, and where it does, the final date for payment is postponed by the same number of days as the delay. The sum you state then becomes the notified sum, and the payer is back to needing a pay less notice to reduce it.

There is a further point here that is worth more than the rest of this article to a firm that applies monthly. Where the contract provides for the payee to make an application for payment, that application can stand as the notice, so a properly made application is not merely a request. It is the document that sets the sum the other side has to actively displace. Whether yours qualifies depends on the contract and on how the application is put together, which is precisely why the format of the thing is not administrative housekeeping.

Where the Act does not reach

Three limits, stated plainly, because assuming the Act applies when it does not is an expensive way to find out.

  • Residential occupiers are excluded. Section 106 takes out construction contracts with a residential occupier, meaning a contract relating principally to operations on a dwelling that one of the parties occupies or intends to occupy as a residence. Work on somebody's own home, contracted directly with them, sits outside this regime entirely, and the contract terms govern instead.
  • A contract does not have to be in writing. Section 107, which restricted the Act to written agreements, was repealed with effect from 1 October 2011 in England and Wales. Oral and partly oral construction contracts carry these rights. Having nothing signed is a serious evidential problem, but it is not a jurisdictional one.
  • Scotland and Northern Ireland run their own versions. The architecture is the same and the statutory instruments are not, so do not lift an English default period onto a Scottish job.
Keeping applications and notices in software

Unibuild's applications for payment module holds each application against the project with its own date, the receipts against it and the retention withheld. Gross applied and gross balance are calculated as at each row's date rather than only as at today. Outstanding value is bucketed into current, thirty, sixty, ninety and one hundred and twenty plus days against the manager responsible. That is the record that answers what was applied for and when, which is the half of a notice argument most firms cannot assemble quickly. The dates come from your contract and somebody in your commercial team owns them. What Unibuild removes is the two days of digging that normally sits between the question and the evidence. Unibuild is bespoke business software for UK trades and specialist contractors: in daily production since 2016, and set up around the way your commercial team already runs its valuations.

Where to start, on Monday

Take one live job and one page. Write down the due date mechanism from the contract, the payment notice period, the pay less period and the final date for payment. Then apply them to the valuation you are about to submit and write the four real dates in the diary of whoever runs the job.

Then do the same for the last three applications you were paid short on. In a good number of cases the reduction arrived without a compliant notice, and nobody checked, because checking requires knowing the dates and having the correspondence to hand. It costs an afternoon and it tends to pay for itself on the first job you run it against.

Sources

Checked against the source rather than against commentary. Where a schedule, a rate or a threshold is definitive on a government site, read it there.

Asked most often

The follow-up questions.

The escalation route when the money still does not arrive is set out in when the contractor above you will not pay.

When must a pay less notice be served?
Before the final date for payment, by the period your contract prescribes. Where the contract does not provide a compliant period, the Scheme for Construction Contracts applies its default: not later than seven days before the final date for payment. The standard forms set their own periods, so the contract is checked first and the Scheme only fills a gap.
What must a pay less notice contain?
Section 111 requires two things: the sum the payer considers due at the date the notice is served, and the basis on which that sum is calculated. A figure with no basis is the most common way these notices fail. The form is otherwise a matter for the contract, so an email can be valid where the contract permits notices by email.
What happens if no pay less notice is served?
The notified sum becomes payable in full on or before the final date for payment, regardless of what the payer thinks the work was worth. That is the basis of a smash and grab adjudication. The payer can generally then start a separate adjudication on the true value of the work, so it is a timing and cash flow advantage rather than a permanent one.
What is the notified sum?
The sum stated in the payment notice that validly stands for that payment cycle. Normally that is the payer's notice under section 110A. If the payer fails to give one, section 110B allows the payee to serve a default notice, and the sum in that notice becomes the notified sum instead, with the final date for payment postponed by the length of the delay.
What is the difference between a payment notice and a pay less notice?
A payment notice states what the payer considers due at the due date and how that figure was calculated. A pay less notice comes later and reduces the sum already notified, giving the ground for the reduction and the new figure. The first sets the number. The second takes money off it. Serving a pay less notice when no payment notice was ever given is a common muddle, and it does not cure the missing first notice.
Who serves the payment notice, the payer or the payee?
Normally the payer, within five days of the due date. Where the contract allows it, a specified person such as a contract administrator may serve instead. If the payer serves nothing, the payee's own application can stand as the default payment notice, and the notified sum becomes the amount the payee applied for. That is the mechanism behind most smash and grab claims, and it starts with a payer who simply did not respond.
How do you serve a pay less notice validly?
In the manner the contract specifies, to the person the contract names, within the window it sets. Check the service clause before you send anything. Email is not always permitted, and sending to the site team instead of the registered office defeats plenty of otherwise valid notices. The notice has to state the sum the payer considers due at the date of the notice and the basis on which it is calculated. A bare figure with no basis is open to challenge.
Can a pay less notice be served late?
No, and lateness is fatal rather than untidy. It must be served no later than the prescribed period before the final date for payment, and a notice served the following day is no notice at all. The sum notified then falls due in full, whatever the true value of the work. Adjudicators apply this strictly, because certainty about the deadline is the whole point of the regime.
Can a pay less notice be withdrawn or corrected?
It can be replaced with a further notice while the window is still open, and once the window closes it stands as served. An error discovered afterwards does not reopen it. The practical answer is to treat the deadline as arriving two days earlier than it does. A mistake found on checking can then be corrected inside the period rather than argued about after it.
Does the Construction Act apply to work on a private house?
Not where the contract is with a residential occupier. Section 106 excludes contracts relating principally to operations on a dwelling that one of the parties occupies, or intends to occupy, as a residence. Work carried out for a developer or a landlord is not caught by that exclusion, so the test is who you contracted with rather than what type of building it is.
Do these rights apply without a written contract?
Yes. Section 107, which limited the Act to agreements in writing, was repealed with effect from 1 October 2011 in England and Wales, so oral and partly oral construction contracts carry the same payment and adjudication rights. Proving the terms of an oral contract is harder, but the rights themselves are not in doubt.
Next step

Know what was applied for, and when.

The whole argument turns on dates and sums that were fixed weeks earlier. Firms lose it because the record of what was applied for takes two days to dig out.

  • Thirty minutes, weekdays, from tomorrow.
  • Nothing to prepare. Bring a job number and we mock that job up.
  • You drive it. There is no slide deck.
  • You keep what you saw as a 14-day trial. No card.