Insight · Health and safety

The CDM documents, and
what has to be in each one.

CDM 2015 names four documents and says what each one has to contain. It says nothing about what they should look like, which is why there is no official template.

Published ·Updated ·11 min read·Written by

Two operatives in coveralls and respiratory protection reading a plan of work on site

CDM 2015 asks for four documents: the pre-construction information, the construction phase plan, the health and safety file, and, on larger jobs, the F10 notification. The regulations say what each one has to contain and who has to produce it. They say nothing about how long it should be, what order it should run in, or what it should look like on the page. That is why there is no official template to download, and why almost every template you can download is either a blank page or a record of somebody else's job.

There is no official CDM template, and that is deliberate

Most people arrive at this subject looking for a blank form. There is not one. CDM 2015 is written as a set of duties and required contents, not as a set of forms. The Health and Safety Executive publishes guidance on what to write, not a document to fill in.

The nearest thing to an exception is the F10, and it is not one. That is an online notification made on the HSE's own service. The form exists because the HSE has to receive the information in a fixed shape, not because your project has to keep a file in one.

The rule

CDM 2015 prescribes content and ownership. It prescribes format nowhere. A document is compliant because it says the right things about this particular job, not because it follows a layout.

Construction (Design and Management) Regulations 2015, regulations 4, 6, 12 and 15

The practical effect is that two compliant construction phase plans can look nothing alike. A plan for a three-week shopfit in an occupied unit and a plan for a nine-month steel frame both satisfy regulation 12. Neither would be much use as the other's starting point, and that is the difficulty a template cannot solve for you.

The four documents, and who writes each

The confusion worth clearing first is about ownership. Three of the four are the client's responsibility to make happen, and only one of those is the client's to write. The regulation number is given for each so you can check any of this yourself.

  1. 01

    Pre-construction information

    Written by
    The client
    By when
    Before designers and contractors are appointed
    Regulation
    2(1), 4(4)

    Regulation 2 defines it as information in the client's possession, or reasonably obtainable, that is relevant to the work and proportionate to the risk. That last word does the work. This is not a standard pack. It is what you already know about this building that the people pricing and designing the job do not.

    The three headings in the definition are the project itself, how it will be planned and managed, and the health and safety hazards. HSE guidance in L153 fills those out:

    • A description of the project and the programme, including any dates that cannot move.
    • The client's own considerations and management requirements, such as access restrictions, working hours and the fact that half the building is still trading.
    • The existing environment and its hazards: the asbestos register, live services, ground conditions, contamination, structural instability, traffic routes.
    • Existing drawings, surveys and any previous health and safety file for the structure.
    • The significant design risks already identified and not yet eliminated.
  2. 02

    Construction phase plan

    Written by
    The principal contractor, or the contractor where there is only one
    By when
    Before the site is set up
    Regulation
    12(1), 15(5)

    Every project needs one. Notifiable or not, two days or two years, one operative or two hundred. Where there is a principal contractor, regulation 12 puts it on them. Where there is only one contractor on the job, regulation 15(5) puts it on that contractor instead, to the same standard.

    The statutory contents are shorter than most people expect:

    • The health and safety arrangements for the construction phase.
    • The site rules.
    • Specific measures for any work that falls within Schedule 3.

    That is the whole list. Everything else in a typical plan is there because it is useful on site, not because regulation 12 asks for it. The plan is also the one document the regulations treat as live: it has to be reviewed, updated and revised as the job changes.

  3. 03

    Health and safety file

    Written by
    The principal designer, then kept by the client
    By when
    Assembled as the job runs, handed over at the end
    Regulation
    12(5) to 12(8)

    Only required where more than one contractor is involved. On a genuine single-contractor job there is no principal designer, and so no file. This is the document people search for as the CDM file, and it is the one most often produced in the last fortnight from whatever anybody can still find.

    Regulation 12(5) asks for information likely to be needed during any subsequent project. Read that literally and it tells you who the reader is: not you, and not the building's occupier, but whoever alters or demolishes the structure in fifteen years. If the principal designer's appointment ends before the project does, the file passes to the principal contractor to finish.

  4. 04

    F10 notification

    Sent by
    The client
    By when
    Before the site is set up
    Regulation
    6, Schedule 1

    Notifiable means one of two things. The first is work scheduled to last longer than 30 working days and to have more than 20 workers on site simultaneously at any point. The second is work scheduled to exceed 500 person days. Either one triggers it, and the first is the part most often read wrong, because both of its limbs have to be met. When a job becomes notifiable covers it at length.

    Schedule 1 lists fifteen particulars, from the site address to the number of contractors expected. The last one is a declaration by the client that they are aware of their duties, and it is the one people are surprised to find they have signed. The notice also has to be displayed where it can be read on site, and kept up to date.

A plan that was right when it was written and never revised is a record of a job that no longer exists.

What a construction phase plan has to address

Schedule 3 is the list that turns a generic plan into a specific one. Where any of these ten is on your job, the plan has to carry specific measures for it. Where none of them is, the plan is still required. It is simply shorter, and a shorter plan that is true beats a long one that was written for another site.

Schedule 3, the work involving particular risks a construction phase plan must address
Schedule 3 categoryWhat it catches on an ordinary job
Burial, engulfment or falls from heightBy a distance the most common of the ten. Any excavation, any unprotected edge, any fragile roof, any work off a scaffold or a mast climber.
Chemical or biological substances requiring health monitoringSilica dust, lead, isocyanates in spray coatings. Anything where the control measure includes surveillance of the person, not just of the task.
Ionising radiation in controlled or supervised areasSite radiography on welds, and density gauges. Rare outside civils and process work.
Work near high voltage power linesOverhead lines on a plot, and live switchgear that cannot be taken out during the works.
Risk of drowningRiver and dock walls, deep excavations that fill, and flooded basements.
Wells, underground earthworks and tunnelsShafts, headings and any confined space the job creates rather than inherits.
Diving with an air supplyMarine and water industry work only.
Caissons or compressed airSpecialist civils.
ExplosivesDemolition and quarrying.
Assembly or dismantling of heavy prefabricated componentsSteel frame, precast, modular units and curtain walling panels. Easily missed on a fit-out that involves a single heavy lift.

Six of those ten never appear on an ordinary refurbishment or fit-out. That is the use of the list. It tells you which parts of the plan have to be specific and evidenced, and leaves the rest to proportionate judgement.

The health and safety file is not the O&M manual

The two arrive at the same meeting, get bound in the same box and are routinely treated as one thing. They answer different questions for different readers, and a file that has been merged into an O&M manual has usually stopped doing its own job.

The O&M manual tells the person running the building how to operate and maintain it. The file tells the person altering or demolishing it what is going to hurt them. HSE guidance in L153 is direct about the contents:

  • A brief description of the work carried out.
  • Hazards that were not eliminated by design or construction, and how they were addressed.
  • Key structural principles, such as bracing and sources of substantial stored energy.
  • Hazardous materials used, such as lead paints and special coatings.
  • How installed plant and equipment is to be removed or dismantled.
  • Health and safety information about equipment for cleaning or maintaining the structure.
  • The nature, location and markings of significant services, including underground cables.
  • As-built drawings of the building, its plant and its equipment.

The same guidance is equally direct about what to leave out, which is the part that would shrink most of the files handed over this year. It should not carry the pre-construction information, the construction phase plan, construction phase risk assessments, method statements, COSHH assessments, contractual documents or accident statistics. None of that helps anybody planning future work, and burying eight useful pages inside four hundred is a way of losing them.

Two roles, one job title. Since 1 October 2023, building work in England also has a principal designer under Part 2A of the Building Regulations. That role is about compliance with the Building Regulations, not health and safety. It is a separate appointment with its own competence requirements, not a renaming of the CDM role.

The same firm can hold both, and where it does the client has to confirm that in writing to them. Where two different firms hold them, they have to work together and share what each one knows.

Whether a free template is enough

Often, yes. CITB publishes the CDM Wizard free for phone, tablet and desktop, and it will produce workable documents for a small project. L153 sets out what each document should contain in enough detail to write one from a blank page. Between the two, a straightforward job can be papered properly without anybody being paid to do it.

The limit is not the quality of the template. It is the size of the job. A template is enough for as long as one person is holding the whole project in their head, because that person is quietly supplying everything the template leaves out. Three things end that, usually in this order:

  1. A second contractor arrives. Now there is a principal designer, a file to assemble, and information that has to be collected from people who do not work for you.
  2. The plan needs revising. Regulation 12 requires it, and the revision is worth nothing until the version on site is the revised one.
  3. Somebody asks for evidence. Not the documents, which you have, but proof that the arrangements in them were actually followed on the days in question.

None of that is a failing of the free tools. They are document generators, and they do that well. They were never meant to be the record of a running job.

What a downloaded plan does on a running job

The problem with a downloaded construction phase plan is not that it is generic on day one. Most plans start generic and get specific as the job is priced and programmed. The problem is that it is never touched again.

A plan written in a word processor and emailed round is revised by whoever happens to have it open. Six weeks in there is the version on the site noticeboard, the version in the principal contractor's sent items, and the version the subcontractor was issued at tender. One of the three is right, and the site is working to whichever is pinned up.

The file has the mirror image of the same problem. It is assembled at the end, from information generated over eighteen months by designers and subcontractors who have since moved on. The parts that cannot be found are the parts nobody recorded at the time. That is a document control problem rather than a CDM one, which is why a better template never fixes it.

Where this touches the platform

The documents themselves are ordinary files, and any system can hold a file. What changes is where the contents come from. Site inductions, toolbox talks, permits, plant checks and RAMS acceptances are recorded as the job runs, against the job. The arrangements set out in the plan then produce their own evidence instead of being reconstructed later. Certificates and competence records carry expiry dates, which is what makes the handover pack assemblable in an afternoon instead of a fortnight. Deciding what Schedule 3 work is on this job, and what to do about it, is judgement, and it stays with the person who knows the site.

Where to start, on Monday

Take the job you are on now and answer three questions in writing. Is there more than one contractor on it? Does it pass either notification limb? And does a construction phase plan exist that describes this site rather than a previous one?

The first answer tells you whether you owe a health and safety file and a principal designer appointment. The second tells you whether an F10 should already have gone. The third is the one that usually produces a silence, and the fix for it is an hour with the plan and the programme, not a better download.

If you want the duties rather than the documents, the CDM checklist runs through them regulation by regulation and prints. If you want the roles and the thresholds, the guide sets out who appoints whom and what each one owes.

Sources

Checked against the source rather than against commentary. Where a schedule, a rate or a threshold is definitive on a government site, read it there.

Asked most often

The follow-up questions.

The duties behind these documents, regulation by regulation, are on the CDM checklist.

What documents does CDM 2015 require?
Four. The pre-construction information, produced by the client before designers and contractors are appointed. The construction phase plan, produced by the principal contractor, or by the contractor where there is only one, before the site is set up. The health and safety file, produced by the principal designer on projects with more than one contractor and handed to the client at the end. And the F10 notification to the HSE, sent by the client, but only where the project is notifiable.
Is there an official CDM 2015 template?
No. CDM 2015 prescribes what each document must contain and who must produce it, and says nothing about format, so there is no approved form and nothing official to download. The one fixed form is the F10, and that is an online notification on the HSE's own service rather than a document you keep. A template can be a useful prompt sheet. It cannot make a document compliant, because that depends entirely on whether the contents describe this job.
What is pre-construction information under CDM 2015?
Information in the client's possession, or reasonably obtainable by them, that is relevant to the construction work and proportionate to the risks involved. Regulation 2 sets it under three headings: the project itself, how it will be planned and managed, and the health and safety hazards. In practice that means the asbestos register, live services, ground conditions, existing drawings and surveys, access and working hour restrictions, and any previous health and safety file. It has to reach designers and contractors before they are appointed, which is what makes it useful rather than a formality.
Who writes the construction phase plan?
The principal contractor, where one has been appointed. Where there is only one contractor on the project, regulation 15(5) places the same duty on that contractor instead. Either way the plan has to exist before the site is set up, and it has to be reviewed, updated and revised as the job changes.
Does every project need a construction phase plan?
Yes. Every construction project needs one, whether or not it is notifiable and however short it is. What changes with the size of the job is the length of the plan, not whether it is required. A two-day job can be covered by a page or two, provided that page describes the actual site rather than a previous one.
What has to be in a construction phase plan?
Three things. The health and safety arrangements for the construction phase, the site rules, and specific measures for any work that falls within Schedule 3. Schedule 3 lists ten categories of work involving particular risks. Among them are falls from height, engulfment, work near high voltage lines, risk of drowning, confined underground work, and the assembly or dismantling of heavy prefabricated components. Everything else in a typical plan is there because it is useful on site, not because regulation 12 asks for it.
What is the CDM file?
Usually a reference to the health and safety file, the document handed to the client at the end of a project involving more than one contractor. It carries what is likely to be needed by whoever works on the structure next. That means hazards that were not designed out, key structural principles, hazardous materials used, how installed plant comes out, the location of significant services, and as-built drawings. It is not the construction phase plan and it is not the operating and maintenance manual.
Who prepares the health and safety file?
The principal designer, starting in the pre-construction phase and revising it as the job runs. If their appointment ends before the project does, the file passes to the principal contractor to finish. At the end it goes to the client, who keeps it, makes it available to anyone who needs it for later work, and updates it when the structure is altered.
Is the health and safety file the same as the O&M manual?
No, and binding them together usually damages the file. The operating and maintenance manual tells whoever runs the building how to operate and maintain it. The file tells whoever alters or demolishes it what is going to hurt them. HSE guidance is explicit that the file should not carry the pre-construction information, the construction phase plan, construction phase risk assessments, method statements, COSHH assessments, contract documents or accident statistics.
Does a single contractor project need a principal designer?
No. The principal designer and principal contractor appointments are triggered by more than one contractor being involved, or being reasonably foreseeable. On a genuine single-contractor job there is neither, and so no health and safety file either. The contractor still has to draw up a construction phase plan, and the client still has to provide pre-construction information.
Is the CITB CDM Wizard enough?
For a small, straightforward project, often yes. It is free for phone, tablet and desktop and it will produce workable documents. The limit is not the quality of what it writes. It is what has to happen afterwards: keeping the plan revised, getting the current version to site, and assembling a file from information other people hold. Then showing that the arrangements were followed. It is a document generator, and it does that job well.
When does a project have to be notified to the HSE?
On either of two tests. The first is work lasting longer than 30 working days with more than 20 workers on site at once. The second is work exceeding 500 person days. Both limbs of the first have to be met, and the client sends the F10 before the site is set up.
Do domestic clients have to produce CDM documents?
The duties largely move off the domestic client rather than disappearing. On a single-contractor project they pass to the contractor. Where there is more than one contractor they pass to the principal contractor, or to the principal designer where that has been agreed in writing. The documents are still required; it is the responsibility for producing them that shifts.
What records does a CDM audit actually ask for?
Rarely the documents on their own. An auditor or an inspector reads the construction phase plan, then asks for evidence that what it describes happened. That means inductions recorded against the people who were on site, toolbox talks signed, permits issued and closed, plant checks done, and competence records in date on the day. That is the gap no template can close, because the evidence is produced by the job rather than written in advance.
How long should the health and safety file be kept?
For the life of the structure. It is not an accounting record with a retention period, because it exists for whoever works on the building next, which may be decades away. The client keeps it, makes it available to anyone who needs it to plan later work, and revises it when the structure changes. Passing it on is part of selling the building.
Next step

Make the plan produce its own evidence.

Bring a live job and its construction phase plan. Half an hour is usually enough to see which of its arrangements would leave a record and which would not.

  • Thirty minutes, weekdays, from tomorrow.
  • Nothing to prepare. Bring a job number and we mock that job up.
  • You drive it. There is no slide deck.
  • You keep what you saw as a 14-day trial. No card.