For steel erection contractors

Half a frame has to
stand up on its own
before anyone goes home.

Lift plans written by an appointed person, accessories examined in date, bolts torqued and recorded, and bracing left in until the frame can carry itself. The engineering is yours. The record behind it is what an inspector and an insurer both ask for. 30+ modules on one account, and a steel erector turns on the handful it needs.

Structural steel erection contractors
The office side

From the lift plan to
the handover.

Portal frames, multi-storey, mezzanines, bridgework or secondary steel: the structure differs, the office side does not.

  1. Putting the steel up is the part an erection contractor already has right. It is the record behind it that decides the year: which lift plan covered which pick, whether the accessory that made it was in date, who torqued the bolts and to what, which welder made the connection and under what procedure, and when the temporary bracing came out.

  2. Unibuild is bespoke business software for UK trades and specialist contractors, built inside a contracting business rather than sold into one. One account carries the plant and equipment registers, the labour run, certification and training records, materials, documents, day works, variations and applications for payment.

All of it on one account, with every erector on it and never a charge per seat.

Built for erection

What steel erection requires, and
what Unibuild provides.

A fit-out job and a steel job look alike in a database. They stop looking alike under the hook, at the bolt torque record, and at the moment the crane leaves and the frame is on its own. Each requirement below is followed by what the platform does about it.

Planned by a named person

Every lift is a planned operation

Lifting operations are planned by an appointed person, supervised by a competent one, and carried out by people trained for the role they hold in it.

  • The appointed person plans the lift; the slinger and the operator execute it
  • The plan names the crane, the accessories, the load, the radius and the ground
  • A change of crane, load or position is a change to the plan, not a judgement call
  • The plan is the document produced after an incident, in its issued version
Plans held against the job, signed at the version issued

Lift plans, method statements and risk assessments are documents against the job with every revision kept, and they are signed on the phone against a version that freezes on submission, by the slinger and the operator rather than by a supervisor on their behalf.

Examined, not just checked

The cheapest item on site stops the lift

Cranes, MEWPs and every chain, strop and shackle behind them carry statutory examinations on their own intervals, and the accessory is examined in its own right.

  • Equipment lifting people is examined at least every six months
  • Lifting accessories are examined at least every six months, separately from the machine
  • Other lifting equipment is examined at least every twelve months
  • A strop out of date is a stopped shift, and it is the item nobody is watching
Accessories as records, not as a box in the van

Each chain, strop, shackle, beam clamp and magnet is its own record with its serial, SWL, examination date and history, on the same expiry page as the cranes and MEWPs. Scanning the item on site returns it, so a check at the compound is a scan rather than a squint at a stamped tag.

Covered by the next trade

Connections are inspected once, then hidden

Bolted and welded connections are checked before the cladding, the fire protection and the concrete cover them, and after that the record is all there is.

  • Preloaded bolt assemblies are tightened to a defined method and recorded
  • Welds are made under a qualified procedure by a welder qualified for it
  • Non-destructive testing is carried out to a specified frequency and scope
  • Nobody is opening the connection up again to check
Inspected at the connection, photographed, signed

Inspection records are completed on the phone against the grid reference and the member, with photographs and a signature, before the connection is covered. The record belongs to the structure rather than to the week it happened in.

Left in until it is not needed

The frame is unstable until it is finished

Temporary bracing, guys and props hold a partly erected frame up, and removing them early is one of the classic ways steelwork comes down.

  • Temporary works carry a design, a check category and a permit
  • The permit to remove bracing is a decision by a named person
  • Partial completion at the end of a shift is the dangerous state
  • Wind is a design case, and it arrives on somebody else's timetable
A register that says what is still holding the frame

Each item of temporary bracing is a numbered record with its design, its check category and its permits, and the permit to remove is a signed, dated act rather than a decision taken at four on a Friday. The reminders engine watches what is still in place.

Everybody is off the ground

Work at height is the standing condition

Erectors spend the day in MEWPs, on netting, on beams and in harnesses, and the access equipment is as regulated as the crane.

  • A MEWP lifts people, so its examination interval is six months
  • Harnesses and lanyards are inspected and have a service life
  • Fall arrest anchor points are part of the temporary works, not an accessory
  • Rescue from height is a plan, not an intention
Access kit and PPE on the same register as the steel

MEWPs, harnesses, lanyards and fall arrest kit are records with their own inspection intervals and service lives, watched on the same page as the cranes. Inspection records are completed on the phone against the item rather than in a book in the van.

Delivered to a programme, not a store

Steel arrives in load order and cannot wait

Members arrive on artics in erection sequence, and a site with no laydown area turns a delivery problem into a programme problem the same morning.

  • Loads are sequenced to the erection order, not to the drawing number
  • A member damaged in transit cannot simply be reordered
  • Bolts, shims and packs are small, critical and easy to run out of
  • A crane standing waiting for steel is the most expensive idle hour in the trade
Loads booked in against the job, photographed on arrival

Deliveries are recorded against the job with a signed note and photographs, so damage is evidenced on the day it lands. Bolts, shims and consumables are held as quantities by item against locations, including a van, with a full movement history.

Counted in the deployment Unibuild was built on, July 2026: one expiry page carrying 376 assets, 141 subcontractor certificates, 84 accreditations, 80 health assessments, 55 instruments and 9 vehicles.

Primary steel
Secondary steel
Bolts and fixings
Temporary bracing
Decking and mesh
Cranes and lifting
Access and fall arrest
Inspection records
The week

An ordinary week in a steel erector,
and the record it leaves.

Six entries from a steel erection contractor's day book. Nothing here asks anybody to remember something on a beam with a wind picking up.

An ordinary week in a steel erector and the record it leaves
Monday, the plan

The appointed person issues the lift plan for the main girders. It goes against the job with its revision, and the slinger and the operator sign it on the phone at the version issued.

Signed, not briefed at
At the compound

Chains and strops are scanned before they go on the hook. One shackle is a fortnight past its examination and is pulled out of the set before it reaches the crane.

Caught at the gate
Tuesday, the delivery

Three artics arrive in erection sequence. One rafter is damaged on the trailer and is photographed against the job before it is lifted off.

Evidenced on arrival
Wednesday, the connections

Bolted connections on grid line C are torqued and recorded against the grid reference, with photographs, before the decking goes on and nobody can see them again.

Recorded before it is covered
Thursday, the bracing

Two bays are ready to have temporary bracing removed. The permit is signed by the named person against the design, rather than agreed between two people on a radio.

Permitted, then struck
The valuation

Extra steel for a plant platform was instructed on site on Tuesday. It was measured, priced on the contract rates and signed where it happened.

Paid for
The test

Eight things steel erection software
has to do.

Written from what actually costs a steel erector money or exposes it, rather than from a feature list. Unibuild is 30+ modules on one account, and an erector turns on a handful of them.

Lifting accessories as individual records

Assets and inventory holds each chain, strop, shackle and beam clamp with its serial, safe working load, examination date and history, rather than as a box of kit. Scanning the item at the compound returns it. This is the cheapest register on the system to keep right and the one that stops a shift when it is wrong. Related: LOLER thorough examination.

Lift plans signed at the version that was issued

RAMS and lift plans are signed on the phone against a version that freezes on submission, by the slinger and the crane operator rather than by a supervisor signing on their behalf. Every revision is kept, newest at the top, so the plan produced after an incident is the plan that was actually in force.

Connection records made before the cladding goes on

Bolt torque and weld inspection records are completed on the phone against the grid reference and the member, with photographs and a signature, at the connection. Once fire protection, decking or cladding covers it, the record is the only evidence that exists, and a record made a week later is not the same document.

Welder and operator competence, by qualification not by name

The training matrix holds welder qualifications by procedure, CPCS or NPORS by category, appointed person, slinger and signaller tickets and medicals, per person, in a grid that colours itself. A welder qualification lapsing is not an administrative problem; it invalidates the connections made after it.

Temporary bracing on a register with a permit to remove

Each item of bracing, guying or propping is a numbered record with its design, check category and permits, and the permit to remove is a signed, dated act by a named person. Reminders and expiry watches what is still in place. Related: the temporary works register.

Access equipment and fall arrest with their own service lives

MEWPs carry a six monthly thorough examination because they lift people, and harnesses and lanyards carry inspections and a service life measured in years rather than uses. Both sit on the same expiry page as the cranes, which is the only way a small firm keeps all three straight.

Deliveries in erection sequence, evidenced on arrival

Loads are booked in against the job with a signed note and photographs, so a member damaged on the trailer is a dated record before it is lifted off. Bolts, shims and packs are held as quantities by item against locations, including the van, with a full movement history.

The compound

What a steel erection contractor holds

Written for the trade rather than for any one firm. Most erectors will recognise eight or nine of these lines and ignore the rest.

What a UK structural steel erection contractor holds, and the tracking quirk in each line
KeyCategoryTypical itemsThe tracking quirk
Lifting accessoriesChains, strops, round slings, shackles, beam clamps, lifting magnetsExamined in their own right every six months, cheap enough to be treated as consumable, and the item that stops the lift
Cranes and lifting plantMobile cranes, spider cranes, telehandlers, chain blocks, tirforsUsually hired rather than owned, so the examination report belongs to somebody else and still has to be held against your job
Access equipmentBoom lifts, scissor lifts, podiums, ladders, netting, edge protectionA MEWP lifts people so its interval is six months, and safety netting is a separate installed system with its own records
Fall arrest and PPEHarnesses, lanyards, inertia reels, rescue kit, anchor devicesCarries both an inspection interval and a service life in years, so a harness expires even if it is never used
Bolts and fixingsPreloaded assemblies, ordinary bolts, holding down bolts, shims, packsSmall, cheap and critical, and the assembly grade matters more than the quantity, so a substitution is a technical decision
Primary steelColumns, beams, rafters, portal frames, trusses, bracing membersDelivered in erection sequence rather than drawing order, and a damaged member cannot be swapped from another job
Secondary steelPurlins, side rails, cleats, stairs, handrail, walkways, plant platformsOrdered late, changed often, and the source of most of the extra work that never gets priced
Decking and meshMetal deck, shear studs, mesh, edge trim, fire stopping to the deckStuds are welded through the deck on site, which makes them a site process with a site record rather than a delivered product
Temporary bracingGuy ropes, props, temporary bracing members, kentledge, anchorsHolds the frame up until it can carry itself, so what matters is not where it is but when it was permitted to come out
Welding equipmentSets, stud welding guns, consumables by batch, ovens, gaugesConsumables are controlled by batch and storage condition, and a gauge is a measuring instrument with a calibration date
TransportArtics, trailers, hiabs, crew vans, welfare unitsA hiab is lifting equipment as well as a vehicle, and loads are sequenced to the erection order rather than to the load sheet
The paperworkLift plans, examinations, bolt records, weld procedures, NDT reportsThe only category with no physical existence and the one that becomes the sole evidence the moment a connection is covered
Regulations

The regimes a steel
erector works under

It is about who planned the lift, what was examined, who was qualified to make the connection, and when the bracing was allowed out. This is the reference version, kept factual.

The regimes a UK structural steel erection contractor works under, and what each requires
RegimeWhat it requires
LOLER 1998Lifting operations are planned by a competent person, appropriately supervised and carried out safely. Lifting equipment is thoroughly examined at least every six months where it lifts people or is an accessory, and at least every twelve months otherwise, or under an examination scheme. On most erection jobs the crane is hired, which means the examination report belongs to the hire company and still has to be held against your job.
BS 7121, the code of practice for safe use of cranesThe industry standard behind the planning duty: the roles of appointed person, crane supervisor, slinger, signaller and operator, the content of a lift plan, and the categories of lift from basic to complex. It is guidance rather than statute, but it is the benchmark an investigation will measure the operation against, and the appointed person is the named individual at the centre of it.
BS EN 1090 and execution classesThe execution of steel structures is governed by an execution class from EXC1 to EXC4, which drives the required welding quality level, the inspection and testing regime, the tolerances and the documentation. A higher class is not more paperwork for its own sake; it changes what has to be checked and recorded on site, and by whom.
Welding procedure and welder qualificationWelds are made under a qualified welding procedure specification by a welder holding a current qualification for that procedure, position and material. Qualifications have validity periods and can lapse. A lapsed welder qualification does not just create an administrative gap; it puts the connections made after it in question, which is why this belongs on a dated register.
Bolting and preloaded assembliesPreloaded bolt assemblies are tightened by a defined method, commonly combined or torque based, and the tightening is recorded. Ordinary bolts are checked for the right grade, length and washers. The connection is inspected before it is covered by decking, fire protection or cladding, after which nobody is opening it again.
BS 5975 and temporary worksTemporary bracing, guying and propping that holds a partly erected frame is temporary works, with a design brief, a design, a check proportionate to a check category, and a permit to load and to remove issued by a named temporary works coordinator. Partial completion at the end of a shift is the state in which frames come down.
Work at Height Regulations 2005Work at height is avoided where reasonably practicable, and where it is not, equipment is selected to prevent falls before it is selected to minimise the distance. For erection that means MEWPs, netting and fall arrest, each with inspection duties, and harnesses carrying a service life as well as an inspection interval. Rescue from height has to be planned rather than assumed.
CDM 2015A steel erector is a contractor, and on a frame-only project sometimes the principal contractor, with duties to plan, manage and monitor. The construction phase plan, the erection method statement and the temporary works register are separate documents that have to agree with each other on the sequence. See the CDM 2015 guide.
Competence schemesCSCS for site access, CPCS or NPORS by category for crane and MEWP operation, appointed person, slinger and signaller qualifications, and welder qualifications per procedure. Several of these are individual tickets renewed on their own timetable rather than one card with one date, which is why a single expiry per person is the wrong shape.
Working time and fatigueEarly starts around crane availability, long travel to a frame that lasts three weeks, and shifts that stretch to get a bay stable before dark all sit under the general duties in the Health and Safety at Work etc. Act 1974 and regulation 3 of the Management Regulations, alongside the Working Time Regulations 1998. See fatigue management.
On the record

Questions steel erectors ask

The questions steel erection contractors actually raise on a demonstration, answered on the record. Open one to read the response.

Lift plansCan lift plans be signed by the slinger and the operator at the version issued?
Yes. Your appointed person plans the lift, and Unibuild holds the plan against the job with every revision kept, newest at the top. The slinger and the operator sign it on the phone against a version that freezes on submission, rather than a supervisor signing on their behalf. After an incident, the plan produced is the plan that was in force.
AccessoriesCan it hold every chain and strop with its examination date?
Yes. Each chain, strop, shackle and beam clamp is its own record with serial, safe working load, examination date and history, rather than a note against a machine. One page watches them all and turns a date red before it passes. Scanning the item at the compound returns it, so a lapsed shackle is pulled out before it reaches the hook.
ConnectionsCan we record bolt torques and weld inspections against grid references?
Yes. Records are completed on the phone at the connection, against the grid reference and the member, with photographs and a signature. A connection covered by decking or fire protection on Wednesday cannot be inspected on Friday, so the record is made where the work is. Your own check sheet is set up to your execution class during implementation.
WeldersWill it track welder qualifications by procedure?
Yes. A welder qualified for one procedure, position and material is not qualified for another, so the training matrix holds the qualification by procedure. CPCS or NPORS by category, appointed person, slinger and signaller tickets and medicals sit on the same grid, which turns amber before a date passes. The WPS itself sits against the job as a document.
Temporary worksCan it hold temporary bracing with a permit to remove?
Yes. Each item is a numbered record with its design, check category, checker and permits. The permit to remove is a signed, dated act by a named person rather than a decision taken over a radio at four on a Friday. One page watches what is still in place, and the design and the check stay with your temporary works designer and coordinator.
Hired cranesThe crane is hired. Whose examination record is it?
The hire company's, and you still need it against your job. The report of thorough examination is held as a dated document on the job record, alongside the operator's ticket and the lift plan. When an inspector asks on the day, all three come from one screen.
AccessAre MEWPs, harnesses and fall arrest kit covered too?
Yes. MEWPs, harnesses, lanyards and fall arrest kit are records with their own inspection intervals and service lives, watched on the same expiry page as the cranes and the accessories. Inspections are completed on the phone against the item rather than in a book in the van.
DetailingHow do the fabricator's drawings reach the team?
Drawings and schedules live against the job with every revision kept, newest at the top, so the erection team works to the current issue. The model stays with the fabricator, and what the team needs from it arrives as the issued drawing.
VariationsSecondary steel changes constantly. Can we get paid for it?
Yes. The supervisor who was asked prices the extra work on the phone, at the moment it is instructed, without showing your margin. Plant platforms, handrail, extra cleats and access steel become dated, priced lines rather than recollections at the valuation. Rate valuations are signed before the crane leaves and feed applications for payment with retention attached.
AdoptionWill erectors actually use it on a frame?
Yes, because a team does three things on the phone: clock in, sign the lift plan and RAMS, and record the connection with a photograph. Everything else stays with the supervisor and the office. Permissions are granted per person, so each role sees only what it needs.
The marketWhat software do UK steel erection contractors use?
Most run a combination: the fabricator's detailing and modelling package, a spreadsheet for the erection sequence and the teams, a folder of lift plans and an accounts package. Unibuild holds the erector's own side on one account: people, competence, lifting accessories, access equipment, site records, variations and the money.
PricingHow is it priced, and do you charge per erector?
One monthly figure covers everything, with unlimited users and no charge per erector. It is sized to the firm when it is quoted and fixed for three years. Taking on more teams never changes the fee, which matters in a trade that flexes hard between frames. How pricing works.
RolloutDo we have to move everything across at once?
No. Most erectors start with lifting accessories and competence, because a lapsed strop or a lapsed ticket stops a shift, then add connection records and variations. Most firms go live in about two weeks, in phases, often starting on one frame. Your existing accessory and people records are migrated for you, and the 14-day trial is the full platform with no card needed.
Other trades

Not quite your
line of work?

The same platform, written for the trade that runs it.
Each of these is a different set of modules
switched on rather than a different product.
Every one is shaped to the firm's own process,
with its own app under its own name.

Other trades
Return slip

Come and try it on one frame.

Half an hour, on your own job and your own kit. Bring a set of lifting accessories and one live frame, and we will set both up in front of you. Unlimited users, never per seat, and fourteen days to try it without a card.

Bring
One set of lifting accessories
Takes
30 minutes
Phone, UK hours
+44 7587 557546
Where it shows first
The first strop caught at the compound
Get a quote
One figure per firm · For UK firms

Right, let’s talk numbers.

Five things about your business. We work your fee out properly and put it in writing the same working day.

What we build for you

  • Your own portalIn the browser, built around your firm
  • Your own appiOS and Android, under your name
  • Everyday AI includedHeavier AI at cost, nothing added
  • One platformEverything in one place, set up by us

Would you rather see it running first? Book a 30-minute demo

Quotation request