When a missing notice
hands you the money.
An adjudication that asks nothing about what the work was worth, only whether the notices were served. What it wins, and the second adjudication that usually follows it.
Published ·5 min read·Written by Unibuild
A smash and grab adjudication asks one question: were the notices served in time. Where the payer served no valid payment notice and no valid pay less notice, section 111 requires it to pay the notified sum in full by the final date for payment, whatever the work was worth. The adjudicator decides on the notices alone and never reaches the valuation.
What it is, and why it exists
The name is industry slang and slightly unfair. What it describes is a party enforcing the statutory payment regime exactly as written.
The Construction Act makes the notified sum payable in full unless a valid pay less notice reduces it before the final date for payment. It sets deadlines for both notices. If the payer misses them, the Act does not invite an adjudicator to work out a fair figure. It says the notified sum is due.
So the adjudication is short and documentary. What was the notified sum, was a payment notice given within five days of the due date, was a pay less notice given before the contractual deadline, and has the final date passed. Four questions, all answerable from documents, and the valuation never comes up.
The defence "but the work was not worth that" is not a defence to this. It is an argument for a different adjudication, brought later.
When you actually have one
Three things have to be true, and the third is where most attempts fall over.
- There is a notified sum. Either the payer gave a payment notice, or it did not and your application validly stood as the default notice under section 110B. If neither exists, there is nothing to enforce.
- No valid pay less notice was served in time. Valid means it specified the sum the payer considered due and the basis of calculation, and in time means before the deadline the contract sets.
- Your own application was properly made. This is the weak point. A payer defending one of these will attack the application first: was it made under the right clause, on the right date, in the right form, stating the basis of calculation. If your application was not compliant, there is no notified sum and the whole thing collapses. That is why how the application is written matters more than anything else here.
What happens next, and why it is the real story
Winning does not end the argument, and any page that implies otherwise is selling you something.
A payer that has paid a notified sum it disputes can start its own adjudication on the true value of the work, and if the true value is lower it can recover the difference. That is the settled position: the notice regime governs what must be paid now, not what the work was ultimately worth.
There is an important sequencing point. The payer generally has to pay the notified sum first before pursuing the true value question. It cannot simply refuse to pay and raise valuation as a defence to the smash and grab. That ordering is the whole commercial value of the exercise.
Which means what you win is this: the cash, now. The other side carrying the cost and effort of the next reference. And a considerably better negotiating position while you hold the money rather than while they do. In an industry where firms fail waiting for cash, that is worth a great deal. It is not the same as being right about the valuation, and going into one believing it is a windfall is how people end up disappointed.
Whether to bring one
Three considerations beyond the merits.
- The cost is not recoverable. Section 108A means you generally cannot recover your own legal or consultancy costs from the other side, so the sum in dispute has to be comfortably larger than the cost of getting it. The fee-capped low value procedure changes that arithmetic on smaller debts and is set out in when the contractor above you will not pay.
- It is a relationship event. There is no polite version. On a repeat client that is otherwise good to work for, exhausting the earlier rungs first is not weakness; it is usually cheaper.
- Your own paperwork gets audited. Bringing one invites forensic scrutiny of your application, your dates and your records. Firms whose records are strong should be untroubled by that, and firms whose records are weak should know it before they start rather than during.
The entire case is documents with dates on them, which is what Unibuild holds. Applications sit against the project with the date each was made, receipts against them, retention withheld captured against the receipt it came off, and gross applied and gross balance calculated as at each row's own date rather than only as at today. Where the job was quoted through the platform, the works schedule draws on the priced sections of that quotation with their tendered values, so the measure behind the application has a documented origin. That is the pack an adjudicator wants and the pack a defending payer will try to pull apart. What the platform does not do is track your statutory notice deadlines or tell you whether a notice was valid: those come from the contract and from advice.
Where to start, on Monday
Take your last three applications and answer four questions on each: was there a notified sum, was a payment notice served within five days of the due date, was a pay less notice served before the deadline, and has the final date passed. That is the whole test, and it takes about ten minutes per application if the records are to hand.
If the answer suggests you have one, take advice before serving anything. This is a fast process with a binding outcome and the drafting of the notice of adjudication matters. Everything above is the shape of the position, not advice on yours.
The follow-up questions.
The notice timetable this all turns on is in pay less notices, and the timetable behind them.
What is a smash and grab adjudication?+
Can the payer bring a true value adjudication afterwards?+
What can defeat a smash and grab adjudication?+
Is a smash and grab worth bringing?+
Does winning a smash and grab mean the work was worth that much?+
More from Insights.
RAMS that hold upWhat an inspector is actually looking for in a risk assessment and method statement, and the difference between a document that exists and one that is doing its job.Read it →
Retention, and the money that goes missing after practical completionWhere cash quietly disappears between the last valuation and the release of the second half of retention, and the four dates that decide whether you ever see it.Read it →
Why field rollouts stall in week threeMost site software is not rejected. It is quietly outlived by the paper route nobody switched off. What the firms that got it to stick did differently.Read it →