Free site diary template

A site diary is the site manager’s record of each day: who was on site, the weather, what arrived and what was done. It also records the instructions received and what held the work up. This one runs over two pages a day, as an editable PDF and a Word document, free to use and reuse.

Editable PDF · 2 pages · 130 KB · Free to use and reuse · Terms

Prefer the links by email? We will send the PDF, Word links to your inbox, nothing else.

Front page of the free site diary template from Unibuild
Format
Editable PDF
Pages
2
Built on
Usual site practice and the contract’s notice and records clauses
Cost
Free, always

What is in the site diary template

2 pages

The day

The project, date, site manager, programme week, the weather morning and afternoon, the temperature and hours lost to weather.

Labour and plant

Each company on site with its trade and numbers, and each item of plant with whether it was working, standing or broken down.

Deliveries, visitors and the work

What arrived and anything short or damaged, who visited or inspected, and the work done by area or activity.

Instructions and delays

Each instruction with who gave it and how, each delay with its cause and length, health and safety notes, photographs and the signature.

Page 2 of the free site diary template from Unibuild: instructions, delays and the record of the day
Page 2 of 2: instructions, delays and the record of the day.

Why the diary matters to the contract

Checked against the source

No statutory form

There is no statutory site diary. It is a contemporaneous record, written on the day by the person in charge, which is what gives it weight.

Usual site practice

Extensions of time

A claim for more time rests on showing what was delayed, when, why and for how long. The diary is where that is recorded as it happens.

Your contract’s extension of time or compensation event clauses

Instructions

A verbal instruction recorded in the diary and confirmed in writing the same day is the start of a variation that gets paid.

Your contract’s instruction clauses

How to use it

Write it before leaving site

A diary filled in a week later is a reconstruction. One written the same day is evidence.

Record the dull days too

A complete diary shows nothing happened as clearly as it shows a delay. Gaps are what a dispute looks at.

Let the day write itself

In Unibuild the clock-ins, deliveries, permits and photographs are already recorded against the job, and the site diary is drafted from the day’s own records. See project management.

Download the editable PDF Editable PDF · 2 pages · 130 KB
Is this site diary template free?
Yes. It is free to download, use and reuse, including on paid work and for clients, with no sign-up and no email address. Download the editable PDF or the Word version.
What should go in a site diary?
The date and weather, the labour on site by company and trade, plant and its status, deliveries, visitors and inspections, and the work done. Then instructions received, delays and their causes, health and safety notes and photographs, signed by the site manager.
Is a site diary a legal requirement?
There is no statutory site diary. Contracts often require records of progress and delays, and the diary is the usual way to keep them. It carries most weight when written on the day.
Who keeps the site diary?
The site manager or the person in charge of the site that day. On larger jobs each contractor keeps their own as well.
How does a site diary help with an extension of time?
A claim for more time has to show what was delayed, why and for how long. A diary entry made on the day, naming the cause and the hours lost, is the strongest record of it.
How does Unibuild handle the site diary?
The day’s clock-ins, deliveries, permits, inspections and photographs are recorded against the job as they happen. The site diary is drafted from those records for the site manager to check and sign. See project management.

More free downloads

All 134 downloads →
Planner · WTR 1998

Staff holiday planner

A leave record per person with entitlement, carry-over and every request approved, a team planner a quarter per page, and the 2026 and 2027 bank holidays by nation. As a PDF, Word and an Excel workbook.

Editable PDF · 6 pages · 1.2 MB

Matrix · MHSWR 1999 regulation 13

Training matrix

One row per person with the expiry of each card and course, a training record per person, and a training needs grid by role. As a PDF, Word and an Excel workbook that turns a date amber at sixty days and red when it passes.

Editable PDF · 3 pages · 557 KB

Check sheet · CDM 2015 regulation 8

Subcontractor approval check sheet

The checks before a subcontractor goes on the approved list: Companies House, CIS verification, insurance, SSIP, the policy, RAMS, competence, right to work, the reverse charge and bank details, then the decision, the register and the review log.

Editable PDF · 3 pages · 423 KB

Next step

The same records,
without the paper.

On the platform these stop being sheets. The check, the person, the date, the signature and the action that followed are recorded as the work runs and retrieved by site.

Get a quote
One figure per firm · For UK firms

Right, let’s talk numbers.

Five things about your business. We work your fee out properly and put it in writing the same working day.

What we build for you

  • Your own portalIn the browser, built around your firm
  • Your own appiOS and Android, under your name
  • Everyday AI includedHeavier AI at cost, nothing added
  • One platformEverything in one place, set up by us

Would you rather see it running first? Book a 30-minute demo

Quotation request