A variation order records a change to the work: who instructed it, what changed, how it is valued and what it does to the programme, signed by both sides. This one is an editable PDF and a Word document with a guidance page on getting the variation paid, free to use and reuse.

Who instructed the change, when, and how: letter, email, site instruction or verbal, with their reference. A verbal instruction is confirmed in writing the same day.
What is added, omitted or altered against the drawing, specification or order it changes, and why: client request, design change, unforeseen site condition, statutory requirement, or an error in the documents.
The cost basis, a quoted sum, measured at contract rates or daywork priced after, the estimate, the agreed value, the daywork sheet numbers, and the extension sought in working days with the activities affected.
Signed for the contractor and the client. The second page sets out the record to keep and how the variation reaches the application for payment under the Construction Act.
The payment mechanism is how a variation gets paid. The application states the sum the contractor considers due at the due date and the basis on which it is calculated. A variation that is not in the application is not in the notified sum.
Housing Grants, Construction and Regeneration Act 1996, section 110AIf the payer disagrees with the sum, their route is a pay less notice before the deadline, stating the sum they consider due and the basis for it. Without one, the notified sum is payable on the final date for payment.
Housing Grants, Construction and Regeneration Act 1996, section 111The JCT and NEC families expect an instruction to be in writing, and each sets out how a verbal instruction is confirmed. Work done on a verbal instruction that was never confirmed is the variation most often disputed.
JCT and NEC standard forms; check your own contractRaise the variation order when the instruction is given, not when the application is due. If the instruction was verbal, send the confirmation the same day and keep it with this order.
A daywork sheet signed each day, photographs, and the materials and plant tickets. The value is argued from the record, and the record is made on the day or not at all.
The variation becomes a line in the application for payment, with the sum and the basis of calculation. In Unibuild a variation is raised on site, priced in the office and carried into the application without being retyped.
A leave record per person with entitlement, carry-over and every request approved, a team planner a quarter per page, and the 2026 and 2027 bank holidays by nation. As a PDF, Word and an Excel workbook.
One row per person with the expiry of each card and course, a training record per person, and a training needs grid by role. As a PDF, Word and an Excel workbook that turns a date amber at sixty days and red when it passes.
The checks before a subcontractor goes on the approved list: Companies House, CIS verification, insurance, SSIP, the policy, RAMS, competence, right to work, the reverse charge and bank details, then the decision, the register and the review log.
On the platform these stop being sheets. The check, the person, the date, the signature and the action that followed are recorded as the work runs and retrieved by site.
UK-built · CDM · CIS · MTD