RAMS template
Risk assessment and method statement for one activity: the sequence of work, a five by five risk matrix, PPE, permits, rescue, and a briefing record signed against the revision.
A plant register lists every item of plant and equipment a firm owns or hires, with where it is and when it was last inspected and is next due. This one carries the PUWER inspection and LOLER thorough examination dates, and an inspection log, as an editable PDF and a Word document, free to use and reuse.

Item, make and model, serial or asset number, owned or hired and from whom, and where it is now.
The inspection interval, when it was last inspected and when it is next due, under PUWER.
For lifting equipment and accessories, the last and next thorough examination under LOLER, and the item’s status.
Every inspection, thorough examination and repair as it happens: the date, the item, who did it, the defects found, the action and the report reference.
Work equipment whose safety depends on its installation, or that deteriorates in use, is inspected at suitable intervals and after exceptional circumstances. The result is recorded and kept until the next inspection is recorded.
PUWER 1998, regulation 6Equipment does not leave the firm, or arrive from another, without physical evidence of its last inspection or thorough examination.
PUWER 1998 regulation 6(4); LOLER 1998 regulation 9(4)Lifting equipment for people and lifting accessories are thoroughly examined at least every six months, and other lifting equipment at least every twelve months, or to an examination scheme. The reports are kept as regulation 11 sets out.
LOLER 1998, regulations 9 and 11A hired telehandler on site is the firm’s to check. Record the hire company and ask for the thorough examination report on delivery.
A defect that makes an item unsafe changes its status on the register at once, not at the next update.
In Unibuild each item has a QR code, its inspections and LOLER examinations are held against it, and the office sees what is due before it lapses. See assets and inventory.
Risk assessment and method statement for one activity: the sequence of work, a five by five risk matrix, PPE, permits, rescue, and a briefing record signed against the revision.
How one activity on one site will be carried out. Two pages of sequence with the controls at each stage, then plant, PPE, permits, rescue and a briefing record.
One hazardous substance: its hazards from the data sheet, who is exposed and how, controls in regulation 7 order, PPE and RPE, storage, spills, first aid, monitoring and review.
On the platform these stop being sheets. The check, the person, the date, the signature and the action that followed are recorded as the work runs and retrieved by site.