RAMS template
Risk assessment and method statement for one activity: the sequence of work, a five by five risk matrix, PPE, permits, rescue, and a briefing record signed against the revision.
UK-built · CDM · CIS · MTD
A method statement sets out how one activity on one site will be carried out, stage by stage, with the controls built into each stage. This one comes as an editable PDF and a Word document, free to use and reuse.
Scope, location and access, the programme, interfaces with other trades, the risk assessment it relies on, and the team with their cards and tickets.
Two pages of stages, from setting up to leaving the area safe, each with what is done, the controls at that stage and the person responsible.
Each item of plant with its checks, certificates and operator competence, and the PPE by type rather than by name.
COSHH references, the permits and plans the work needs, the rescue plan, and dust, noise and waste.
Twenty signatures against the revision, taken on the day and before the work starts.
Every contractor must plan, manage and monitor the construction work under their control, so that it is carried out without risks to health and safety, so far as is reasonably practicable.
CDM 2015, regulation 15(2)For demolition or dismantling, the arrangements must be recorded in writing before the work begins, usually as a method statement.
CDM 2015, regulation 20(2)For other work a method statement is not required by law. HSE describes it as an effective and practical way to plan, manage and monitor the work, and principal contractors usually ask for one.
HSE construction guidanceThe hazards and controls come from the risk assessment, which is a legal duty. With five or more employees, its significant findings must be recorded.
Management of Health and Safety at Work Regulations 1999, regulation 3One activity on one site: this sequence, this access, these people. A method statement that describes the trade rather than the job is the one sent back.
Each stage says what is done and the controls that apply at that moment, so the team meets the control at the point it matters.
Everyone signs against the revision before they start. When the sequence, the team or the conditions change, revise it and brief it again.
Risk assessment and method statement for one activity: the sequence of work, a five by five risk matrix, PPE, permits, rescue, and a briefing record signed against the revision.
One hazardous substance: its hazards from the data sheet, who is exposed and how, controls in regulation 7 order, PPE and RPE, storage, spills, first aid, monitoring and review.
Every hazardous substance held, with its data sheet date, main hazard, WEL, storage, COSHH assessment and review date, plus update and review logs.
On the platform these stop being sheets. The check, the person, the date, the signature and the action that followed are recorded as the work runs and retrieved by site.