Stopping work for non-payment,
without breaching your contract.
A statutory right with narrow conditions and real leverage. What has to be true before you can use it, what the notice must say, and what walking off without one costs.
Published ·Updated ·5 min read·Written by Darshan Parmar, Founder

Section 112 of the Construction Act gives a statutory right to suspend performance of any or all of your obligations where the notified sum has not been paid in full by the final date for payment, after giving at least seven days' written notice stating the ground. You are entitled to a reasonable amount for costs and expenses reasonably incurred, and to time for the delay.
Start with the risk, not the right
The failure here is almost never a firm neglecting to use section 112. It is a firm walking off site because it has had enough, without serving anything, and turning a strong position into a weak one overnight.
Leaving site without the statutory notice is not exercising a right. It is potentially a repudiatory breach of your own contract, and the other side's response is to bring in a replacement, charge you the difference, and set the whole thing against what it owes you. Firms have lost more this way than the debt they were angry about.
The notice is the entire difference between those two outcomes, and it costs one email.
Serving the notice turns walking off site from a breach into a remedy. It takes ten minutes and it is the only thing standing between the two.
What has to be true first
Three conditions, and the first is narrower than people assume.
- The notified sum has not been paid in full by the final date for payment. Not that you are owed money generally, not that an application is being disputed, and not that a payment is a few days late against your own expectations. There has to be a notified sum, and the final date has to have passed. If you are unsure what those are, the payment timetable calculator works them out.
- You have given at least seven days' written notice of your intention to suspend, stating the ground on which it is being given.
- The seven days have run and the sum is still unpaid. Suspending on day five is not exercising the right.
What the notice says
Short and specific. Five things: the contract, the application and the notified sum, the final date for payment and that it has passed, the fact that no valid pay less notice was served if that is the case, your intention to suspend performance under section 112 if payment is not received, and the date on which suspension will begin.
Send it by a method the contract recognises for notices, and keep proof of sending. Diarise the seventh day. A notice that is obviously correct is frequently the last step required, because the other side's advisers read it and tell them the position.
You can suspend part of it
The provision allows suspension of performance of any or all obligations, and the partial option is the one most summaries skip and most firms should consider first.
Full suspension is a blunt instrument that damages the programme, the client relationship and often your own labour planning. Suspending a specific obligation can be more proportionate and just as effective: stopping a particular work package while continuing elsewhere, or withdrawing from an obligation that is costing you money to keep performing.
Whatever you choose, describe it precisely in the notice. A vague suspension invites an argument about whether what you did was what you said.
What you get back
Two entitlements that firms routinely fail to claim, both of which are in the section rather than being favours.
A reasonable amount for costs and expenses reasonably incurred as a result of exercising the right. That covers the real consequences: demobilising and remobilising, plant standing or being returned and re-hired, and labour you could not redeploy. Record these as they happen rather than reconstructing them, because reasonable has to be evidenced.
Time. The period of suspension and the time reasonably needed to resume are not held against you on programme, which matters because the alternative is being charged delay damages for a delay the other side caused by not paying.
Before you get here
Suspension sits at the third rung of the escalation ladder, and it works best when the rungs below it have been used properly: a default payment notice where the payer served none, then a dated written demand setting out the contractual position. Both are free, and a meaningful proportion of disputes settle at the second. The full sequence is in when the contractor above you will not pay.
Also worth knowing what it is not. Suspension is not termination, and threatening termination when you mean suspension is a serious escalation with different consequences. And none of this applies where the Act does not, principally contracts with a residential occupier, covered in what the Construction Act actually gives you.
Two things decide whether this right is usable, and both are records. Whether the conditions are met turns on what was applied for, on what date, what notice came back and whether the final date has passed. Unibuild's applications for payment module holds exactly that position against each project, with its dates and receipts. And what you recover afterwards turns on evidencing costs reasonably incurred, which is why plant movements with signed notes, labour recorded against the job, and a dated site diary matter after a suspension as much as during a claim. The final date for each application can be worked out in the payment timetable calculator, and the decision to serve notice stays with a named person. Unibuild is bespoke business software for trades, in daily production since 2016, and each firm's system is shaped to the way that contractor already works.
Where to start, on Monday
Do not draft a notice. Establish the facts first: for the oldest unpaid application, is there a notified sum, has the final date passed, and was a valid pay less notice served. If all three point the right way, you have the right and it is worth taking advice on the notice before serving it.
If they do not, you are on a lower rung than you thought, and the useful step is the free one: the default payment notice or the dated written demand. This is a statutory remedy with real consequences either way, so treat the above as the shape of it rather than advice on your contract.
Sources
Checked against the source rather than against commentary. Where a schedule, a rate or a threshold is definitive on a government site, read it there.
- Section 112, Housing Grants, Construction and Regeneration Act 1996 legislation.gov.uk
- Housing Grants, Construction and Regeneration Act 1996 legislation.gov.uk
The follow-up questions.
The rungs below this one are in when the contractor above you will not pay.
Can I stop work if I have not been paid?
Does suspending work for non-payment put me in breach of contract?
How much notice do I have to give before suspending?
Can I suspend only part of the work?
Can I recover costs after suspending for non-payment?
Can I claim an extension of time for the period of suspension?
Does suspending affect my retention or a performance bond?
What if the contract says I may not suspend?
What happens if I walk off site without serving notice?
When is suspension better than adjudication?
Know the position before you act on it.
Suspension is a statutory right with a seven-day notice and a precise trigger. Get the dates wrong and a lawful step becomes a breach.
- Thirty minutes, weekdays, from tomorrow.
- Nothing to prepare. Bring a job number and we mock that job up.
- You drive it. There is no slide deck.
- You keep what you saw as a 14-day trial. No card.
More from Insights.
When the contractor above you will not payThe remedies run in a fixed order and each one costs more than the last. What to do first, what every step is worth, and the rung most disputes never get past.Read it →
What the Construction Act actually gives youSix rights that apply whether or not your contract mentions them, and whether or not anything was ever signed. What each one is, and how far it reaches.Read it →
Charging interest on a late payment, and the sums nobody claimsStatutory interest runs at eight per cent above base, and a fixed compensation sum sits on top of it that almost nobody asks for. Both are automatic entitlements rather than favours.Read it →All 10 articles on getting paid.