A free site start-up checklist: 21 checks in plain English, each with the regulation behind it. What has to be in place before anyone starts work, not the week after.

Published · Last reviewed

Start here

What has to exist
before work starts.

Almost everything expensive about a project is decided in the fortnight before anybody turns up. CDM 2015 is explicit that the construction phase plan must exist before the construction phase begins and that welfare must be in place from day one, not from the first delivery. This is the list of what has to be true on the morning of week one.

The hard deadlines, who holds them, and what starting without them costs+
The hard ones
Three things are unambiguously before-you-start, not soon-after: the construction phase plan (Reg 12(1)), welfare facilities (Reg 13(4)(c) and Sch 2), and the F10 where the job is notifiable (Reg 6). Starting without them is a breach on day one, whatever happens afterwards.
When F10 is needed
Construction work scheduled to last longer than 30 working days with more than 20 workers on site simultaneously at any point, or to exceed 500 person days. The client gives the notice and it is displayed on site. Notification changes nobody's duties.
Services are the killer
Striking a live service is one of the most common causes of serious injury on UK sites. HSG47 is the guidance: drawings, then a scan, then trial holes, then safe digging practice. Drawings on their own have never been enough.
Proportionate, not thick
A construction phase plan for a two-week domestic job is a few pages. The test in Reg 12 is that it sets out the health and safety arrangements, site rules and any significant risks. A 90-page template nobody reads fails that test as surely as no plan at all.
What this checklist covers
21 checks across three sections: 7 before you are on site at all, 8 setting the site up, 6 in the first week. Each entry names the regulation it comes from, or says plainly where it is good practice.
Before mobilisation

Before you mobilise.

Appointments, notification and the plan. None of this can be done from site.

Setting up

Setting the site up.

The physical setup. Get it wrong now and you live with it for the whole job.

The first week

The first week.

What turns a set-up site into a managed one.

A starting point for your own review, not legal advice. Always check against the current regulations and HSE guidance. Put your own company in the field above and the PDF carries your name instead of ours. Ticks, notes and site details stay in your browser. Nothing is sent to us.

Download

Or use it as a printable template.

Download the blank site start-up checklist as a PDF, or work through the list above on screen and save that instead, dated and carrying the site, the person who prepared it and the score out of 21. Nothing is gated: no email address to hand over, no account to create, no trial to start.

Download the blank template (PDF) PDF · 21 checks · 70 KB · free, no sign-up
A blank template
The PDF above carries all 21 checks, each with the regulation it comes from and a ruled line for the evidence, the owner and the date. Print it and fill it in on site.
Or a completed record
Work through it on screen first and Save as PDF produces a dated record of what was in place and what was not, with your evidence notes typed against each check.
Your ticks stay in your browser
Ticks, notes and site details are held on this device only. Nothing is sent to us, so you can close the tab and pick it up tomorrow on the same machine.
Your name on it, not ours
Put your company in the field above and the downloaded PDF carries your letterhead instead of Unibuild's. It is free: a sheet you hand to a client should be able to have your name on it.

Worth knowing. A checklist filled in once, the week of an audit, is a snapshot. The evidence behind it is either generated as the work runs or reconstructed under pressure, and that is the difference between a template and a record. It is also what the health and safety module is for.

By duty holder

The same start-up,
read by role.

These are the same checks above, grouped by whoever normally answers for them.

Client

Items 1, 2 and 3 of the pre-mobilisation section. Appointments in writing, pre-construction information and the F10 are yours and cannot be delegated by silence.

Principal designer

Pre-construction information, design risk and opening the health and safety file: items 2 and 5 before mobilisation, and item 6 of the first week.

Principal contractor

The plan, the whole setting-up section and the inspection regime. If the site is not fit to work on in week one, it is your name on it.

Project manager

The commercial half: insurance, appointments, licences, neighbours and the programme that decides whether welfare is there before the groundworkers are.

Site manager

The first-week section. Induction, RAMS briefings and the first emergency test are what convert a compound into a managed site.

Temporary works coordinator

Item 4 of the first week, and it is a gate not a formality: nothing gets loaded until the design is checked and signed.

After the checklist

You shouldn't need
this checklist.

On the platform the appointments, insurances, surveys and the plan sit against the project record from the day it is created, so week one is a reading exercise rather than a scramble.

Questions

What people ask before
they use the checklist.

The questions that come up most often around a site start-up checklist, answered against the regulations rather than around them.

When does the construction phase plan have to be ready?+
Before the construction phase begins. Regulation 12(1) of CDM 2015 is written that way deliberately: the plan is a precondition of starting, not a document produced in the first fortnight. It must be proportionate to the job and it has to be reviewed and revised as the work proceeds.
Does welfare have to be there on day one?+
Yes. Regulation 13(4)(c) and Schedule 2 require suitable welfare facilities to be provided from the start of the construction phase and maintained throughout. A common and expensive mistake is programming the welfare unit to arrive with the first delivery rather than before the first worker.
When is a project notifiable to the HSE?+
When the construction work is scheduled to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or when it is scheduled to exceed 500 person days. The client gives notice on form F10 and it is displayed on site. Notification changes nobody's duties: a job that is not notifiable still needs a construction phase plan.
Do we need an asbestos survey before we start?+
If the building was constructed or refurbished before 2000 and the work is intrusive, you need a refurbishment and demolition survey, not just a management survey. The duty to manage in Regulation 4 of the Control of Asbestos Regulations 2012 sits with whoever controls the premises, but it is the contractor who disturbs it who is at risk.
Are utility drawings enough to locate services?+
No, and treating them as enough is how people get hurt. HSG47 sets the sequence: obtain plans, use a cable avoidance tool to scan, dig trial holes to confirm, then use safe digging practice. Plans show intent at the time of installation, not where the service actually is after thirty years of alteration.
Is this the same as a pre-construction checklist?+
Broadly yes, and the terms are used interchangeably on UK sites. Some businesses split them: a pre-construction list covering appointments, information and the plan, then a start-up or mobilisation list covering the physical setup. This one covers both, in the order the work actually happens.
Is this checklist free, and do I have to sign up?+
It is free and there is nothing to sign up for. No email address, no account, no trial. Tick it above, add evidence notes if you want them, and download the result as a PDF. Ticks, notes and site details are held in your own browser and nothing is sent to us.
Can I put my own company name on the PDF?+
Yes. There is a company field beside the site and the person completing it, and whatever you put there becomes the letterhead on the downloaded PDF instead of ours. It is a free checklist: a sheet you hand to a client should be able to carry your name.
Does Unibuild do this for me?+
No supplier makes a business compliant, and be wary of one that says its software does. What the platform does is hold the record: the check, the person, the date, the photograph and the action that followed, retrievable by site and by date with an audit trail behind it. The duty stays with the duty holder. More on the health and safety module.
Next step

Before the next
one starts.

Run this over the project you are mobilising and see what is programmed for week three that should be there in week one.