A free project handover and close-out checklist: 21 checks in plain English, each with the regulation behind it. The health and safety file, the O&M manuals and the defects period.
Published · Last reviewed
What handover
actually has to hand over.
Handover is where a well-run job quietly becomes a badly documented building. The construction phase plan dies with the project; the health and safety file outlives it and is read by whoever maintains, refurbishes or eventually demolishes the structure. CDM 2015 makes the principal designer prepare it and hand it to the client, and the client keep it available. Most disputes at close-out are about information nobody collected while it was free to collect.
The file against the plan, who holds what, and why retention is the client's problem+
- The file is not the plan
- Two documents, two audiences. The construction phase plan is for the people building the job and finishes when they do. The health and safety file is for whoever works on the structure afterwards. Both sit under Reg 12, and a handover that confuses them hands over the wrong one.
- Who prepares it
- The principal designer prepares and updates the file through the project and passes it to the client at the end. Where the PD's appointment finishes before the project does, Reg 12(7) passes the job to the principal contractor. That handover is itself commonly missed.
- What goes in it
- Residual hazards, key structural principles, hazardous materials left in place, services and how to isolate them, and information for safe cleaning and maintenance. It is not a dump of every document from the job.
- Who keeps it
- The client, available to anyone who needs it, and it must be passed on if the structure is sold. A file handed over on a USB stick that nobody can find in five years has technically been handed over and practically has not.
- What this checklist covers
- 21 checks across three sections: 7 on the health and safety file, 8 on the technical and commercial handover, 6 on closing the job out properly.
The health and safety file.
Seven checks on the document that outlives the project, and on whether it is usable rather than merely delivered.
The technical handover.
Eight checks on the information the building needs to be operated, and the money closed.
Closing the job out.
Six checks that stop a finished project generating work for two more years.
This browser is not letting the page store anything, so the checklist will count and print correctly but will be empty again if you reload. Save as PDF before you leave.
A starting point for your own review, not legal advice. Always check against the current regulations and HSE guidance. Put your own company in the field above and the PDF carries your name instead of ours. Ticks, notes and site details stay in your browser. Nothing is sent to us.
Or use it as a printable template.
Download the blank project handover checklist as a PDF, or work through the list above on screen and save that instead, dated and carrying the site, the person who prepared it and the score out of 21. Nothing is gated: no email address to hand over, no account to create, no trial to start.
- A blank template
- The PDF above carries all 21 checks, each with the regulation it comes from and a ruled line for the evidence, the owner and the date. Print it and fill it in on site.
- Or a completed record
- Work through it on screen first and Save as PDF produces a dated record of what was in place and what was not, with your evidence notes typed against each check.
- Your ticks stay in your browser
- Ticks, notes and site details are held on this device only. Nothing is sent to us, so you can close the tab and pick it up tomorrow on the same machine.
- Your name on it, not ours
- Put your company in the field above and the downloaded PDF carries your letterhead instead of Unibuild's. It is free: a sheet you hand to a client should be able to have your name on it.
Worth knowing. A checklist filled in once, the week of an audit, is a snapshot. The evidence behind it is either generated as the work runs or reconstructed under pressure, and that is the difference between a template and a record. It is also what the health and safety module is for.
The same handover,
read by role.
These are the same checks above, grouped by whoever normally answers for them.
Principal designer
The whole file section. Reg 12 makes it yours through the project, and where your appointment ends first it must be handed to the principal contractor deliberately, not by default.
Principal contractor
The file where it has passed to you under Reg 12(7), plus demobilisation and the waste paperwork. The last week on site is where records get lost.
Client
Receiving the file, keeping it available, and passing it on if the structure is sold. It is a duty, not a delivery, and it survives your project team.
Project manager
The technical and commercial section end to end. Most of what is missing at handover was free to collect three months earlier.
Facilities or operator
The training and the O&M information. If the people who will run the building were not in the room, the handover has not happened.
Commercial
Final account, retention dates and warranty assignment. Retention released late is the most predictable dispute in construction.
You shouldn't need
this checklist.
On the platform the certificates, as-builts, surveys and sign-offs accumulate against the project as the job runs, so the file is assembled rather than reconstructed.
What people ask before
they use the checklist.
The questions that come up most often around a project handover checklist, answered against the regulations rather than around them.
What is the difference between the health and safety file and the construction phase plan?+
Who prepares the health and safety file?+
Is a health and safety file always required?+
What should not go in the health and safety file?+
Who keeps the file after handover?+
When should we start compiling the file?+
Is this checklist free, and do I have to sign up?+
Can I put my own company name on the PDF?+
Does Unibuild do this for me?+
On the one
finishing now.
Run this over the project closing this month and see how much of the file is still on somebody else's laptop.