What a quantity surveyor does,
and what they need from site.
A quantity surveyor turns what happened on site into money: valuations, variations, cost reports and the final account. What the job involves at each stage, and the four records from site that decide how well it is done.
Published ·6 min read·Written by Darshan Parmar, Founder

A quantity surveyor manages the money on a construction job. They work out what it should cost, value what has been built, price every change and agree the final account. RICS calls them the cost managers of construction. On a contractor’s side the QS turns what happened on site into money, and every figure they produce rests on records made on site.
What does a quantity surveyor do?
The work follows the job from first budget to final account. A QS on a large project may cover one stage. In a trade firm, one QS often covers all of them across several jobs at once.
| Stage | What the QS does | What it rests on |
|---|---|---|
| Cost planning | Estimates what the building should cost and keeps the design inside it. | Drawings, the brief and cost data, measured under NRM1 |
| Measurement and tender | Measures the work into a bill of quantities and prices or checks tenders. | Drawings and specifications, measured under NRM2 |
| Interim valuations | Values the work done each month for the payment application or certificate. | Measured progress, materials on site, instructions and dayworks |
| Change | Values variations and assesses claims for loss and expense. | Written instructions and records made at the time |
| Cost reporting and CVR | Compares cost to date with value to date, job by job, every month. | Labour, plant, materials and subcontract costs against each job |
| Final account | Agrees the final value of the contract with the other side. | Everything above, kept for the life of the job |
Building measurement follows the RICS New Rules of Measurement. NRM1 sets the rules for cost estimates and cost plans, and NRM2 for bills of quantities, which go on to value interim payments and varied work.
Client QS and contractor QS
There are two sides to the job. A consultant quantity surveyor, often called a PQS, works for the client. They set the budget, run the procurement and value the work for the contract administrator, who certifies what the contractor is paid.
A contractor’s quantity surveyor works for the firm doing the work. They price it, apply for payment, manage subcontractors’ accounts and report whether each job is making money. Senior contractor QSs are often called commercial managers. Both sides can be chartered through RICS, and both value the same work from opposite ends.
The monthly valuation
Most UK construction work is valued monthly. RICS guidance on interim valuations sets out how it is done, and three of its points shape what the QS needs:
- The whole job is revalued each time, not just the work done since the last valuation.
- Work is valued as properly executed, and a site visit, with inspection or measurement, checks that it has been done. Whether it was done properly is for the contract administrator.
- Variations go in under a written instruction, and a daywork sheet signed and dated by authorised people is a record the QS does not second-guess.
Materials count once they are delivered to or beside the works, protected and not brought early. RICS treats a valuation within 5% of the true figure as acceptable on contracts up to £2.5m, and within 2.5% above that.
A valuation is only as good as the last record from site. The QS can measure the work, but cannot measure what nobody wrote down.
Cost value reconciliation
On the contractor’s side, the monthly valuation has a twin. Cost value reconciliation, or CVR, compares the value of the work with the cost of doing it, job by job, at each month end. RICS describes it as the project’s profit and loss statement, including costs for goods and services used but not yet paid for.
The gap between what was applied for and what the work is worth is called over or under measure. A job that looks profitable on applications and loses money on cost is found here, or not at all. How to run a cost value reconciliation.
The four things a QS needs from site
Most of the friction between the office and the job comes down to four records. When they arrive complete and on time, the QS spends the month valuing. When they do not, the QS spends it chasing.
- Progress, dated and located. What is complete, where on the job, and on what date. Photographs help when they carry the date and the area. RICS practice information suggests annotating them with the date and time.
- Every instruction, written down the day it is given. An instruction on the slab is worth nothing at valuation unless it is in writing. RICS practice information suggests numbering every change on a register, updated at least monthly.
- Daywork sheets signed that week. Once a sheet is signed and dated by authorised people, the QS cannot replace it with their own estimate. Without one, the work is measured or valued fairly, and that is where the argument starts.
- Labour, plant and materials against the right job. Hours, deliveries and plant on hire, booked to the job that used them. Without it, the cost side of CVR is a guess, and so is every rate in the next tender.
Why the record has to be made at the time
The Society of Construction Law’s Delay and Disruption Protocol is direct about it. Records of progress, delay and disruption must be made as the works progress, not afterwards. They should state facts, offer no opinions and, where practicable, be signed by both sides.
Its list of useful records reads like a site manager’s day. It names daily site reports with weather, labour, deliveries, hours and plant, and dated progress photographs. It adds daily labour and plant allocation, a log of major deliveries, and timesheets. A QS assembling a claim from memory is working against all of it. More on that in getting paid for variations you were told to get on with.
How to become a quantity surveyor
Most quantity surveyors qualify through a degree accredited by RICS, a graduate scheme or the Level 6 Chartered Surveyor degree apprenticeship. Chartership, as MRICS, comes through the RICS Assessment of Professional Competence, which usually takes around two years after the degree.
The National Careers Service gives a salary range of £26,000 for a starter to £70,000 for an experienced QS, for 37 to 40 hours a week. Contractors, consultancies, developers, housing associations, local authorities and specialist contractors all employ them.
In Unibuild the four records come from the job as it runs. Operatives clock in by QR code, so hours land against the job they were worked on. Site diaries, progress photographs and day works are captured daily on the phone, with the weather and the trades on site logged. Day works are signed by the client’s representative before and after, with start and finish times and photographs, then priced in the office and claimed in the valuation. Variations are priced and signed on site and become a variation on the project in one action. Each application carries its due date, final date for payment and the notices against it.
RICS publishes the valuation, change and commercial management documents cited here as practice information, which is advisory, and has said new UK practice guidance will replace them. This article follows the versions in force on 30 October 2026.
Sources
Checked against the source rather than against commentary. Where a schedule, a rate or a threshold is definitive on a government site, read it there.
- RICS: Quantity surveying and construction, APC pathway guide (December 2025) rics.org
- RICS: Interim valuations and payment, 1st edition rics.org
- RICS: Commercial management of construction, 1st edition rics.org
- RICS: Change control and management, 1st edition rics.org
- RICS: New rules of measurement (NRM) rics.org
- Society of Construction Law: Delay and Disruption Protocol, 2nd edition scl.org.uk
- National Careers Service: Quantity surveyor nationalcareers.service.gov.uk
- Prospects: Quantity surveyor job profile prospects.ac.uk
The follow-up questions.
What makes an application for payment survive the QS on the other side is in an application for payment that does not come back rejected.
What does a quantity surveyor do?
What does a QS do on site?
What is the difference between a PQS and a contractor’s QS?
What is an interim valuation?
What is CVR in construction?
What records does a quantity surveyor need from site?
How do you become a quantity surveyor?
How much does a quantity surveyor earn in the UK?
Does Unibuild give a QS the records from site?
More from Insights.
An application for payment that does not come back rejectedFour reasons account for most rejections, and none of them is the price. What the document has to contain, what has to sit behind it, and the date that matters more than the total.Read it →
Getting paid for variations you were told to get on withThe entitlement is rarely the problem. The evidence is. What stands up when the instruction was verbal, and the one email that changes the argument.Read it →
Daywork sheets: getting them signed and paidA daywork sheet is the record of instructed work nobody could price in advance. What it should hold, what the signature agrees to, how daywork rates are built, and how it reaches the valuation intact.Read it →All 14 articles on commercial.