Temporary electrical supply,
and the paperwork behind it.
Why site power runs at 110 volts, what has to be inspected every three months, and why the isolation permit is the document that decides whether anybody is allowed to work on it.
Published ·Updated ·16 min read·Written by Darshan Parmar, Founder
Temporary electrical supply on a UK construction site comes from a builder's supply off the local network, or from a generator. Either one feeds a site installation built to BS 7671 Section 704. Portable tools run at 110 volts, centre tapped so that nothing is more than 55 volts to earth. The installation is certified before use and inspected at least every three months.
A temporary electrical installation on a construction site is judged by the same standards as a permanent one, and inspected considerably more often. The cable and the boards are the straightforward part. What decides whether the installation is defensible is the initial verification certificate, the periodic inspection interval, and the isolation permit that says who was allowed to work on it and when.
- Power comes from a builder's supply, which is cheap to run and slow to arrange, or a generator, which is the reverse. Long jobs usually have both, in sequence.
- A builder's supply is usually TT. The site provides the earth electrode, the RCD and a lockable meter enclosure.
- Tools run at 110V centre tapped to earth. Yellow is 110V, blue 230V and red 400V, under BS EN 60309-2.
- Certify before use, inspect at least every three months, and certify every alteration.
- Nobody works on it without safe isolation under regulations 12 to 14 of the Electricity at Work Regulations 1989, and a permit naming who holds the lock.
Builder's supply or generator
A builder's supply is a metered temporary connection from the local distribution network operator. A generator is available at once but costs more every week it runs, so most long programmes start on a generator and change over to the builder's supply.
The first commercial decision on a site is where the power comes from, and it is usually made on programme rather than on cost.
A builder's supply is a temporary connection from the local distribution network operator, taken from the network at the point where the permanent supply will eventually land. It is metered, the energy is charged at commercial rates, and it is quiet. The difficulty is lead time. A new connection involves an application, a quotation, a wayleave or easement where the cable crosses third party land, and a scheduled excavation. On a constrained urban site that can run to months, which is why the decision has to be made at tender rather than at mobilisation.
A generator is available immediately and costs more to run. It brings fuel deliveries, a bunded tank, a refuelling procedure, and exhaust emissions that are increasingly regulated in low emission zones. It also brings noise limits, set by the site's own planning conditions or by a prior consent under section 61 of the Control of Pollution Act 1974. Hybrid units with battery storage have changed the arithmetic on smaller sites, because the engine runs only to recharge rather than continuously.
| Point | Builder's supply | Generator |
|---|---|---|
| Available | After the network operator's works, often months | The day it is delivered |
| Running cost | Metered energy at commercial rates | Hire, fuel and servicing, every week |
| Noise and emissions | None on site | Planning conditions, section 61, emission zones |
| Fuel storage | None | A bunded tank and a refuelling procedure |
| Certification | Initial verification, then periodic inspection | The same, for everything after the generator |
| Best fit | Programmes longer than a few months | Enabling works, short jobs and remote sites |
Most sites of any length end up with both, in sequence. The generator carries enabling works and the early programme, the builder's supply takes over once the connection is in, and the changeover is a planned event with an isolation and a re-energisation rather than something that happens on a Friday afternoon.
Getting a builder's supply connected
A builder's supply takes two applications: the connection from the distribution network operator, and a supply contract with an energy supplier. The network operator brings the cable to a meter position. The site usually provides the enclosure, the earth electrode and the RCD.
The network operator for the area quotes for the physical works: the service cable, any excavation and the meter position. Temporary supplies are commonly single phase at 32A for small jobs and three phase at 63A or more for larger sites. Size it from the site's load, cabins and hoists included, rather than from the last job. The energy supplier then registers and supplies the meter, which is a separate contract with its own lead time.
Earthing is where a builder's supply differs from a house. Most are supplied as TT, which means the site drives its own earth electrode instead of using the network operator's earth terminal. UK Power Networks, for example, supplies its builder's connections as TT. It says they cannot meet the bonding requirements of the Electricity Safety, Quality and Continuity Regulations 2002. BS 7671 points the same way from the installation side. Section 704 rules out a PME earthing facility for a construction site installation unless every extraneous-conductive-part is reliably connected to the main earthing terminal. On a site that changes every week, that is rarely practicable.
In practice the site provides a lockable weatherproof enclosure for the cut-out and meter, an earth electrode, and an RCD after the meter. All three are installed to the current edition of BS 7671. Some network operators also specify the duct for their cable and where it runs. Read the operator's own requirements before the groundworker digs. A meter position in the wrong place is a second visit and a second charge.
The regulations and standards that apply
Temporary electrical installations on UK construction sites are governed by the Electricity at Work Regulations 1989 and regulation 25 of CDM 2015, which are law. BS 7671 Section 704, BS 7375 and HSE guidance describe how to meet them.
| Document | Status | What it covers |
|---|---|---|
| Electricity at Work Regulations 1989 | Law | Systems built and maintained to prevent danger (regulation 4). Isolation and live working (regulations 12 to 14). |
| CDM 2015, regulation 25 | Law | Energy distribution installations located, checked and marked. Overhead and underground cables. |
| Control of Pollution Act 1974, section 61 | Law | Optional prior consent from the local authority for noise from the works, generators included. |
| BS 7671:2018+A4:2026, Section 704 | Standard | Construction and demolition site installations, including RCD protection and earthing. |
| BS 7375:2010 | Code of practice | How electricity is distributed on construction and demolition sites. |
| BS EN 60309-2 | Standard | Industrial plugs and sockets, keyed and colour coded by voltage. It replaced BS 4343. |
| IET Guidance Note 3 | Guidance | Inspection and testing to BS 7671, including the three month interval for construction sites. |
| HSE HSG141 and HSG107 | Guidance | Electrical safety on construction sites, and maintaining portable equipment. |
Only the first three are law. The rest are the accepted way of meeting it. HSE says that following its guidance will normally be enough to comply, and an installation built to BS 7671 is the recognised route to satisfying the Electricity at Work Regulations. Section 704 does not cover site offices and canteens. Those are installed to the rest of BS 7671, as ordinary installations.
Why site power runs at 110 volts
Portable tools on UK construction sites run at 110 volts from a transformer centre tapped to earth, so neither conductor is more than 55 volts from earth. HSE recommends cordless tools or this 110V system on site, although no regulation names the voltage.
Portable tools on UK construction sites run at 110 volts from a centre-tapped transformer. The centre tap is earthed, which means the voltage between either conductor and earth is 55 volts rather than 110. That is the entire point of the arrangement. A fault to earth, or a person completing a circuit to earth, sees 55 volts instead of the 230 volts a domestic supply would present.
It is worth being precise about the status of this. Nothing in the Electricity at Work Regulations 1989 names 110 volts. What regulation 4 requires is that systems are constructed and maintained so as to prevent danger, so far as is reasonably practicable. Reduced low voltage is the accepted way of achieving that for portable equipment on a construction site, it is what BS 7671 Section 704 and HSE guidance describe, and it is what an inspector expects to find. A site running 230 volt tools without a very good documented reason is not breaching a specific numbered rule. It is failing the general one, which is worse, because there is no technicality to argue about.
Lower voltages appear where the risk is higher again. Handlamps in confined or damp locations run on SELV, and portable lighting in particularly conductive locations is the usual example. The principle is the same each time: as the consequences of a fault get worse, the voltage available to cause one comes down.
Distribution across the site
Site distribution is the chain of assemblies and cables from the incoming supply to the socket a tool plugs into. Regulation 25 of CDM 2015 requires it to be suitably located, periodically checked and clearly indicated, and BS 7375 is the code of practice for laying it out.
Between the incoming supply and the tool at the end of the lead sits a distribution arrangement that has to survive being on a construction site, which is a harsher environment than almost anything a permanent installation deals with.
On most sites the chain has four links. The incoming supply feeds a main distribution assembly carrying the main isolator and RCD protection. That feeds outgoing assemblies around the site at 400 or 230 volts. Transformers step down to 110 volts, and outlet units carry the yellow sockets the leads plug into. The assemblies are built to BS EN 61439-4, the product standard for construction site assemblies.
The practical requirements are ordinary and routinely missed. Enclosures need an ingress protection rating suited to being outside in a British winter. Residual current devices need to be present where required and, critically, need to be tested rather than assumed. Cables need routing where plant will not run over them and where they will not be the thing somebody trips on at the top of a stair. Where a cable does have to cross a route, it needs a ramp or a catenary rather than a plank.
Section 704 of BS 7671 sets where the RCDs go. Where automatic disconnection is the protective measure, every circuit feeding a socket outlet rated up to 32A needs a 30mA RCD. Circuits feeding larger sockets need one rated at no more than 500mA. Reduced low voltage circuits are protected a different way, which is one more reason the 110V system is preferred.
Regulation 25 of CDM 2015 sits over all of this. Energy distribution installations must be suitably located, periodically checked and, where necessary to prevent danger, clearly indicated. Where overhead cables are a risk, they are directed away from the risk area or the power is isolated. If neither is reasonably practicable, warning notices go up alongside barriers, suspended protection where vehicles pass beneath, or measures giving the same level of safety. No work that could disturb an underground service starts until suitable steps have been taken to prevent the danger. That regulation is why buried and overhead services get marked and guarded before plant moves, and it is enforced against sites that treat cable protection as tidiness rather than as a control measure.
The colour coding that stops a cross-connection
Construction site plugs and sockets follow BS EN 60309-2, the standard that replaced BS 4343. Yellow is 110 volts, blue is 230 volts and red is 400 volts three phase, and each voltage is keyed so that a plug cannot fit the wrong socket.
Site connectors are colour coded by voltage, and the colours are not decoration. Yellow is 110 volts, blue is 230, red is 400 volt three phase. The system arrived as BS 4343, which was replaced by BS EN 60309-2, the UK edition of the international IEC 60309 standard. It is on every site in the country.
| Colour | Voltage | Typical use on site |
|---|---|---|
| Yellow | 110V | Portable tools, task lighting and festoon, from a centre tapped transformer |
| Blue | 230V | Site cabins, welfare units and fixed equipment |
| Red | 400V three phase | Hoists, cranes, larger plant and feeds to distribution assemblies |
What makes it work is the mechanics, not the colour. The pins sit at different clock positions for each voltage, and the barrels are keyed. A 110 volt tool cannot be pushed into a 230 volt socket by somebody in a hurry in poor light, which is the whole design intent. The protection does not depend on anybody reading the colour.
Which is why the failures are always the improvised ones. A plug rewired onto the wrong body. An adaptor made up on site. A damaged socket with the keyway broken out of it. Each defeats a safeguard built to work when nobody is paying attention. Each is found at inspection, long after it was made.
Initial verification and the three month cycle
A temporary site installation needs initial verification and an Electrical Installation Certificate before it is used, then periodic inspection and testing. IET Guidance Note 3, the inspection and testing guidance to BS 7671, recommends a maximum interval of three months on construction sites.
This is the part that separates a well-run temporary installation from one that merely works.
Every new installation, including a temporary one, requires initial verification: inspection and testing before it is energised for use, and an Electrical Installation Certificate recording the result. That certificate is not paperwork for its own sake. It is the document that establishes the installation was safe at the moment it was handed over, which is the baseline everything afterwards is measured against.
Then it is inspected again, periodically, and the interval on a construction site is short. IET Guidance Note 3 recommends a maximum period of three months between periodic inspections for construction site installations, against three to five years for most commercial and industrial premises. The reason is not that site electricians are careless. It is that a construction site changes weekly, equipment is moved and damaged, and an installation that was correct in March may have four unrecorded alterations by June.
Two points about that three month figure, because both are commonly got wrong. It is a recommended maximum interval in guidance, not a statutory deadline, so nobody is prosecuted for being at three months and a week. And it is a maximum rather than a target, so an installation that takes heavy abuse should be looked at more often than that, not less.
Portable equipment is a separate regime running alongside. In-service inspection and testing of the tools plugged into the installation is its own discipline with its own intervals, and it is the one that generates the volume of records, because there are hundreds of items rather than one installation. The tool intervals are covered in full in how often to PAT test site power tools.
| What | Source | Interval |
|---|---|---|
| Whole installation, before use | BS 7671 | Initial verification and an Electrical Installation Certificate |
| Whole installation, in service | IET GN3 | Periodic inspection and test at least every three months |
| Alterations and additions | BS 7671 | Certified before the altered part is put into use |
| Fixed RCDs | HSE HSG107 | Checked daily or every shift, combined inspection and test every three months |
| 110V portable tools | HSE HSG107 | Weekly user check, monthly formal visual inspection, combined test every three months |
| 230V portable tools | HSE HSG107 | Check every shift, weekly formal visual inspection, combined test monthly |
| Emergency lighting | BS 5266-1 | Monthly function test, annual full duration test |
Safe isolation, and the permit that authorises it
Safe isolation on a construction site rests on regulations 12 to 14 of the Electricity at Work Regulations 1989. Isolate the supply, stop it being re-energised, and work live only where dead working is unreasonable. A permit to work records who isolated what, and who holds the lock.
Most serious electrical incidents on construction sites do not happen because an installation was badly designed. They happen because somebody worked on something they believed was dead.
Regulation 12 of the Electricity at Work Regulations 1989 requires suitable means of cutting off the supply and isolating equipment. Regulation 13 requires adequate precautions to prevent equipment made dead from becoming live while work is carried out. Regulation 14 restricts work on or near live conductors to circumstances where it is unreasonable to make them dead and suitable precautions are taken. Between them, those three regulations describe a procedure rather than a state of mind.
The procedure in practice is a sequence: identify the correct point of isolation, isolate it, secure the isolation with a lock and a unique key held by the person doing the work, prove the test instrument on a known source, test the conductors dead, then prove the instrument again. That last step catches the instrument that failed between the two tests, and it is the step people skip.
What ties it to the commercial side of the business is the permit. A four part isolation permit records who authorised the isolation, what was isolated and where, who took the permit and accepted responsibility for it, and the switching schedule showing the order in which points were made dead and in which they will be restored. It is signed on issue, signed on acceptance, signed on cancellation and signed on final sign-off, and it carries a validity window that the issuer sets rather than the person asking for it.
That document is what makes the difference three years later when somebody asks who was allowed to remove the lock. A verbal arrangement between two people who have both since left the company is not an answer.
The permit regime is the part of this Unibuild holds directly, in its permits to work. An isolation permit is raised on a phone on site against the job, so it inherits the job number, the project and the client. The phone runs the firm's own staff app, published under the contractor's name and icon rather than a software vendor's. The permit carries the authorised person and the person in charge, the points isolated, the switching schedule, and four signatures: issue, acceptance, cancellation and final sign-off. The issuer sets the final validity window separately from the one requested, so a permit granted only until two o'clock says so. It renders as a numbered PDF generated from the record on demand, which means there is no stale copy and nothing to file.
Electrical sign-off sheets certifying an installation before energisation sit in the same family. Inspection dates for the installation and the emergency lighting go into the reminders engine alongside calibration and accreditation renewals. An interval that has run over is a row that has already coloured itself. What the record closes is the gap between having done the work correctly and being able to prove it.
Emergency lighting, and the bit that gets forgotten
Temporary emergency lighting on a construction site is tested to BS 5266-1: a monthly function test and an annual full duration test, each written down. The record, more than the lighting, is what usually fails.
Temporary emergency lighting is part of the same installation and it is inspected on its own cycle. On a site with escape routes through unfinished areas, it is also the system most likely to have been altered without anybody recording it, because luminaires get moved as the works progress and the escape route changes with them.
The recurring failure is not the lighting itself. It is the test record. A monthly function test and an annual duration test are the regime BS 5266-1 sets out, both of which produce a result that has to be written down somewhere findable. On a temporary installation that "somewhere" is frequently a logbook in a cabin that leaves site with the cabin.
What belongs in the tender, and what gets left out
A temporary electrical tender has to price the recurring work, not only the install and the strike. That means periodic inspections, certified alterations, emergency lighting tests, isolation standing time and the collection.
Firms that supply temporary electrical services tender against measured rates, which means the margin is decided before anybody turns up. The items that get missed are consistent, and they are all recurring rather than one-off.
- The periodic inspections. A twelve month programme carries four of them at three month intervals. A tender priced on the installation and the strike alone has three inspections in it that nobody costed.
- Alterations. Sites change. Every alteration to a temporary installation needs its own certification, and on a rate-based contract that is a variation to be measured and signed rather than a favour.
- The emergency lighting test regime. Monthly function tests over a long programme add up to real labour.
- Standing time on isolations. An isolation requested by another trade, for their work, is chargeable time. It is also the item most often given away because the permit was raised verbally and there is no record it happened.
- The collection. Cable, boards, transformers and festoon all have to come back, be counted and be repaired. That is covered in off-hire, and the charges that keep running.
Where to start, on Monday
Take one live site and find two documents: the initial verification certificate for the temporary installation, and the date of the most recent periodic inspection. If either takes more than ten minutes to produce, that is the finding, and it is a more useful one than anything an audit would tell you.
Then look at how the last isolation was authorised. If the answer is that somebody rang somebody, the permit regime is the thing to fix first, because it is the only one of these documents that protects a named individual rather than the company.
Sources
Read at source, on legislation.gov.uk, Health and Safety Executive, electrical.theiet.org and library.ukpowernetworks.co.uk. Each link opens in a new tab, so this page stays open. Last checked against this article on 10 November 2026.
- Electricity at Work Regulations 1989 (opens in a new tab)
- Construction (Design and Management) Regulations 2015 (opens in a new tab)
- CDM 2015, regulation 25: energy distribution installations (opens in a new tab)
- Control of Pollution Act 1974, section 61 (opens in a new tab)
- HSE: electrical safety on construction sites (HSG141) (opens in a new tab)
- HSE: maintaining portable electrical equipment (HSG107) (opens in a new tab)
- HSE: electricity, systems in buildings (opens in a new tab)
- IET: BS 7671 Wiring Regulations (opens in a new tab)
- UK Power Networks: temporary builder's connections (opens in a new tab)
The follow-up questions.
The certificates that expire quietly, and the register that catches them, are covered in the certificates that expire without anybody noticing.
What is a temporary builder's supply?
How do I get a temporary electricity supply for a building site?
What regulations apply to a temporary electrical installation?
Is 110V a legal requirement on construction sites?
What do the colours on site plugs and sockets mean?
How often must a temporary electrical installation be inspected?
What certificate does a temporary electrical installation need?
How often should RCDs on site be tested?
Who is responsible for the temporary supply on site?
Can a generator be used instead of a mains connection?
What is a four part isolation permit?
What happens at the changeover from temporary to permanent power?
Every permit, against the job that needed it.
The isolation happened. The question three years later is who authorised it, until when, and whether anybody signed to accept it.
- Thirty minutes, weekdays, from tomorrow.
- Nothing to prepare. Bring a job number and we mock that job up.
- You drive it. There is no slide deck.
- You keep what you saw as a 14-day trial. No card.
More from Insights.
What a temporary water supply on site actually costsThe cost splits three ways, and only one of the three is the water. The connection is quoted, the consumption is metered, and the compliance is the part that gets left out of the price.Read it →
Site welfare, and what Schedule 2 actually requiresToilets, washing, drinking water, somewhere to change and somewhere to sit down. The list is short, it is legally specific, and "so far as is reasonably practicable" does not apply to most of it.Read it →
The certificates that expire without anybody noticingInsurance, cards, plant inspections, training and first aid all run out on different dates, and nothing about your file changes on the day one of them does. What has to watch them.Read it →All 3 articles on site services.


