Insight · Commercial

Preliminaries, the cost
most firms forget to price.

Everything that makes the job possible and appears on no drawing: supervision, welfare, access, plant standing, insurance, and the time before and after. Why it gets under-priced and how to stop.

Published ·5 min read·Written by Unibuild

Preliminaries are the costs of running the job rather than of doing any particular item of work: supervision, welfare, access, temporary services, insurances, plant standing and the time either side. Most of them are driven by how long the job lasts, and most firms price them as a percentage of the measured work, which is why they are the most under-priced part of a tender.

Time-related costs priced as a percentage

Here is the whole argument, and it is arithmetic rather than opinion.

Your site manager costs the same per week whether the gang lays a hundred metres or fifty. So does the welfare unit, the scaffold standing, the site insurance and the compound. Those costs are a function of weeks.

Price them as a percentage of the measured work and you have tied a weekly cost to a quantity. On a job that runs to programme, the percentage is roughly right by accident. On a job that takes three weeks longer, the measured work has not changed, so the percentage has not changed, so you have three weeks of supervision, welfare and standing plant with no revenue attached to them. That is not an overrun cost. That is a pricing error that only becomes visible when the programme moves.

Price prelims as a percentage and every week the job slips comes straight out of margin, because the quantity that generated the percentage did not slip with it.

It also explains a symptom that puzzles firms and is described in how to tell whether you are underpricing: the jobs that make money are the small ones. Small jobs are short, so a percentage covers their limited time-related cost. The bigger and longer the job, the more of it is weeks, and the further a percentage falls behind.

What actually belongs in prelims

Wider than most firms allow for. In four groups.

  • People not fixing anything. Site manager or supervisor, foreman where they are not on the tools, banksman, gateman, and the proportion of a contracts manager's week this job consumes.
  • The site itself. Welfare and its servicing, cabins, compound, temporary power and water, lighting, hoarding and signage, security, waste and skips, cleaning, and consumables that belong to no single item.
  • Access and plant that stands. Scaffolding for the duration rather than for the erection, towers, hoists, and any plant that is on the job whether or not it is working. This is where off-hire discipline turns into a pricing question.
  • Everything either side of the work. Mobilisation and demobilisation, setting out, surveys, the health and safety documentation the job requires, testing and commissioning, snagging, the operation and maintenance manuals, and the time it takes somebody to close the job out. That last group is the most consistently forgotten, because it happens when everyone has mentally moved on.

Build them from the programme

The correction is straightforward and takes an hour longer than a percentage.

  1. Take the programme, in weeks. If you do not have one, that is the first problem, because you are pricing a duration you have not estimated.
  2. Split the list above into fixed and time-related. Mobilisation is fixed: it happens once. Supervision is time-related: it happens every week. Most items are obviously one or the other.
  3. Price the fixed items as sums and the time-related items as a weekly rate.
  4. Multiply the weekly rate by the programme, and add the fixed sums.
  5. Write the weekly rate down where you can find it, because it is the number you will need the moment anybody asks for an extension of time or a prolongation cost.

That last step is worth more than the pricing improvement. A firm that knows its prelims cost per week can answer a delay claim with a figure. A firm that priced a percentage has no number at all and ends up negotiating against one the other side produced.

When the client wants them cut

Prelims are visible in a tender and clients push on them, sometimes on the reasonable basis that they look like overhead.

Two responses that work better than reducing the number. Reduce the duration, not the weekly rate: if the client wants the prelims down, the honest lever is a shorter programme, and offering that turns a haggle into a joint problem. Or move a genuinely discretionary item out of prelims and into an option the client can decline, so what remains is defensible line by line.

What not to do is shave the weekly rate to win the job while planning the same site set-up. That is a decision to lose the difference, taken at tender, and it will not be recovered.

On a subcontract package

Worth a note, because subcontractors are often told prelims are the main contractor's problem.

Some are, genuinely: you are not paying for the welfare or the hoarding. But a subcontract package still carries its own time-related cost, and it is regularly priced at zero. Your supervision while your gang is on site. Your plant standing between the times you can get access. Your time attending progress meetings. Mobilising twice because the programme moved and you left and came back.

That last one deserves naming, because remobilisation is the most common uncompensated cost in subcontracting and it is entirely a prelims question. If the programme moves and you are asked back, that visit has a cost, and whether you recover it depends on whether it was ever a number.

Where this touches the platform

Two things make prelims answerable rather than theoretical. Knowing the actual duration, which is a matter of what happened rather than what was planned: site diaries and daily records with the trades on site and the weather captured give you the real weeks, which is what a prolongation argument turns on. And knowing what was actually spent on the time-related items, which means supervision hours landing against the job from clock-ins at dated cost rates, and plant showing as committed cost while it stands. Where a project was quoted through the platform the priced sections carry through, so the prelims allowance and the prelims spend can be compared rather than estimated. Unibuild will not build your programme.

Where to start, on Monday

Work out your prelims cost per week for one live job. Supervision, welfare, standing plant, insurance, everything that recurs, divided into a weekly figure. Most firms have never had this number and it takes half an hour.

Then look at the last job that ran over. Multiply the weeks it slipped by that figure. That is what the overrun actually cost you in prelims alone, and it is usually a larger number than anybody in the business had assumed.

Asked most often

The follow-up questions.

Where prelims sit in the whole method is in how to price a construction job.

What are preliminaries in a construction quote?+
The costs of running the job rather than of doing any particular item of measured work: supervision and site management, welfare and cabins, temporary power, water and lighting, hoarding, security, waste and cleaning, scaffolding and plant that stands, insurances, and everything either side of the work such as mobilisation, setting out, testing, snagging and closing the job out.
Why should preliminaries not be priced as a percentage?+
Because most of them are driven by time rather than by quantity. A site manager and a welfare unit cost the same per week regardless of how much work is done. Tie that weekly cost to a percentage of measured work and a job running three weeks late carries three weeks of supervision and standing plant with no extra revenue, because the measured quantity has not changed.
How do you price preliminaries properly?+
From the programme. Split the items into fixed, such as mobilisation which happens once, and time-related, such as supervision which happens every week. Price the fixed items as sums and the time-related items as a weekly rate, then multiply the weekly rate by the programme duration. Record the weekly rate, because it is the figure any delay or prolongation claim turns on.
What should I do if a client wants the preliminaries reduced?+
Reduce the duration rather than the weekly rate, because a shorter programme genuinely reduces time-related cost and turns a haggle into a joint problem. Alternatively move a discretionary item out of prelims into an option the client can decline. Shaving the weekly rate while planning the same site set-up is a decision to lose the difference, taken at tender.
Do subcontractors need to price preliminaries?+
Yes, and they are regularly priced at zero. You may not be paying for welfare or hoarding, but a package still carries your own supervision while the gang is on site, your plant standing between access windows, time attending progress meetings, and remobilising if the programme moves and you are asked back. Remobilisation is the most common uncompensated cost in subcontracting.
Read next

More from Insights.

Steel reinforcement being fixed in a deep excavationReducing risk··3 min readThe contractor above you has gone into administrationWhat to do in the first seven days, where you rank, and the three things worth securing before anybody tells you to stop.Read it A modern office interiorReducing risk··3 min readWarning signs the firm above you is in troubleThe accounts tell you eighteen months late. What tells you now is behaviour: valuations shaved without explanation, payment slipping a week at a time, and the commercial team turning over.Read it A hand writing on documents at a deskTax and CIS··4 min readGetting gross payment status, and keeping itThree tests, and the one that catches firms out is the compliance test, which now looks at VAT as well. What qualifying takes, and what a single late return costs you.Read it Two colleagues at a desk after reaching an agreementTax and CIS··3 min readVerifying a subcontractor with HMRCThe step that decides the rate you deduct at, and the one firms do after paying rather than before. What verification returns, how long it lasts, and who carries the cost of getting it wrong.Read it A team working together at a shared tableCommercial··4 min readWhat an employee actually costs youSalary is about four fifths of it. Employer National Insurance at 15% above a £5,000 threshold, the pension, and the on-costs of putting somebody on a site make up the rest.Read it Site team on a concrete slab with reinforcement beyondCommercial··4 min readSubcontractor or employee, and why HMRC may disagreePaying somebody through CIS does not make them self-employed. The tests that decide it, the arrangements that fail them, and the declaration you sign every month saying you have considered it.Read it A row of tracked excavatorsSubcontractors··5 min readWhy you cannot find reliable subbiesIt is treated as a hiring problem and it is a retention problem. The firms that get the good trades are the ones that are straightforward to work for, and most of that is commercial rather than social.Read it Operatives working among steel reinforcement on a slabPlant and assets··5 min readKnowing what plant you own and where it isThe losses are quiet: kit that walks between sites, kit hired because nobody could find the one you have, and kit written off that is still in a container. What a register has to do to stop it.Read it An electrician testing at a distribution boardPlant and assets··4 min readOff-hire, and the charges that keep runningHire runs until the item is off-hired, not until you finish with it. A preventable loss that every contractor recognises and almost nobody has a process for.Read it Tower cranes above a building under constructionHealth and safety··4 min readGateway 2, and what it does to a programmeApproval has to be granted before construction starts, and the wait has improved sharply: a median of 22 weeks at June 2026 against 43 a year earlier. What that means if you are not the applicant.Read it A modern office interiorWinning work··4 min readBidding for public sector work for the first timeThe Procurement Act 2023 changed how this works in February 2025, and one requirement is absolute: register on the Central Digital Platform or you cannot be awarded a contract at all.Read it Two people working through a drawing at a desk with laptopsChoosing software··5 min readWhere the office hours actually goNot in the work. In assembling positions from four places, retyping what site already recorded, and chasing paperwork that exists but cannot be found. How to measure your own before deciding anything.Read it Technical drawings and tools on a workbenchCommercial··6 min readHow to price a construction job without guessingA method rather than a feeling: measure, build the rate from labour, plant and materials, add the site costs that carry the job, recover overhead, then decide margin. The order matters and the last two steps are where firms lose money.Read it A hand writing on documents at a deskCommercial··5 min readHow to tell whether you are underpricingYou will not find it in the jobs that went wrong. It is in the ones that went fine and returned less than they should have. A test you can run on last year in an afternoon.Read it Site team on a concrete slab with reinforcement beyondCommercial··5 min readDay rate or fixed price, and when each one costs youNot a preference. A decision about who carries the risk of the unknown, and there is a right answer for most jobs once you are honest about what you do not know.Read it Tower cranes above a building under constructionCommercial··5 min readMaterials went up after you quotedThe average tells you nothing. Structural steel rose 13.1% in the year to May 2026 while cement fell 5.0%, and a quote is only exposed to what it is built from. What protects a price, and what does not.Read it Two colleagues at a desk after reaching an agreementWinning work··5 min readGetting on a main contractor's approved listThe application is the easy half. What decides it is the evidence pack behind it, and what gets a firm quietly dropped afterwards is rarely the work.Read it A hand writing on documents at a deskWinning work··6 min readSSIP, CHAS, Constructionline and what replaced PAS 91An acronym map with the money attached. Which schemes are health and safety only, which are full pre-qualification, what mutual recognition actually saves you, and why PAS 91 is no longer the answer.Read it A technical drawing being marked up at a deskTax and CIS··5 min readWhat counts as construction work under CISThe included list is wider than most firms assume and the excluded list catches out exactly the trades that read it. Plus the mixed contract rule, which decides more cases than either list.Read it Two people working through a drawing at a desk with laptopsTax and CIS··5 min readCIS monthly returns, the date and the penaltiesThe nineteenth, every month, whether or not you paid anybody. What the penalty ladder actually looks like, and the declaration on the return that carries more weight than the figures.Read it A modern office interiorTax and CIS··5 min readEnd user statements, and what they switch offIt has to be in writing, it comes from your customer rather than from you, and without it the reverse charge applies by default. What the statement says and where it belongs.Read it Site operative in a hard hat and safety glassesHealth and safety··5 min readThe certificates that expire without anybody noticingInsurance, cards, plant inspections, training and first aid all run out on different dates, and nothing about your file changes on the day one of them does. What has to watch them.Read it Site team on a concrete slab with reinforcement beyondHealth and safety··5 min readWhen an HSE inspector turns up on siteWhat they can do, what they ask to see and in what order, what a Notification of Contravention means, and what the visit can cost you at £188 an hour.Read it Operatives working among steel reinforcement on a slabHealth and safety··5 min readRIDDOR, what has to be reported and by whenThree different clocks run on three different categories, and the one firms miss is the fifteen days, which counts from the accident rather than from the day you realised.Read it Tower cranes above a building under constructionHealth and safety··5 min readWhen a job becomes notifiable, and who tells the HSETwo thresholds, either of which triggers it, and a duty that sits with the client rather than with you. How to work out whether your job crosses them.Read it An electrician testing at a distribution boardHealth and safety··5 min readWhich CSCS card, and who actually checks itSeven colours, different qualifications behind each, and a five year clock on most of them. What each card is for, and why it is not a legal requirement but still stops you at the gate.Read it A team working together at a shared tableChoosing software··6 min readWhy WhatsApp fails as a site recordIt is the system most sites actually run on, and it works right up until somebody asks a question about March. Six specific failures, and the one that arrives when a person leaves.Read it Two people working through a drawing at a desk with laptopsChoosing software··5 min readWhere spreadsheet job costing breaksNot when it gets complicated. When two people open it, when committed cost is not in it, and when the true position is a week old by the time anybody has assembled it.Read it Two colleagues at a desk after reaching an agreementChoosing software··6 min readChoosing construction management software, and what to actually compareEvery product demos well. A buyer's checklist written to be useful even if you buy from somebody else, including the five questions vendors answer badly.Read it A hand writing on documents at a deskChoosing software··5 min readXero for contractors, and where the accounts package stopsIt handles CIS properly and it is a good ledger. What it is not built to hold is the job: the measured schedule, the valuation, the retention and the cost you have committed but not yet been invoiced for.Read it A technical drawing being marked up at a deskChoosing software··5 min readDocument control, and the revision everybody was working toBuilding to a superseded drawing is expensive, common, and almost never anybody being careless. What has to be true for the right revision to reach the person holding the tool.Read it Technical drawings and tools on a workbenchGetting paid··5 min readAn application for payment that does not come back rejectedFour reasons account for most rejections, and none of them is the price. What the document has to contain, what has to sit behind it, and the date that matters more than the total.Read it Steel reinforcement being fixed in a deep excavationGetting paid··5 min readGetting paid for variations you were told to get on withThe entitlement is rarely the problem. The evidence is. What stands up when the instruction was verbal, and the one email that changes the argument.Read it A modern office interiorGetting paid··5 min readWhen a missing notice hands you the moneyAn adjudication that asks nothing about what the work was worth, only whether the notices were served. What it wins, and the second adjudication that usually follows it.Read it A row of tracked excavatorsGetting paid··5 min readStopping work for non-payment, without breaching your contractA statutory right with narrow conditions and real leverage. What has to be true before you can use it, what the notice must say, and what walking off without one costs.Read it A hand writing on documents at a deskGetting paid··5 min readCharging interest on a late payment, and the sums nobody claimsStatutory interest runs at eight per cent above base, and a fixed compensation sum sits on top of it that almost nobody asks for. Both are automatic entitlements rather than favours.Read it Site operative in a hard hat and safety glassesGetting paid··6 min readWhat the Construction Act actually gives youSix rights that apply whether or not your contract mentions them, and whether or not anything was ever signed. What each one is, and where it stops.Read it Site team on a concrete slab with reinforcement beyondSubcontractors··6 min readVetting a subcontractor before you instruct themNine checks, what each one is actually protecting you from, and the two that firms skip and then discover matter. Most of it is twenty minutes and free.Read it Two people working through a drawing at a desk with laptopsReducing risk··6 min readCredit checking the firm above you, free, in twenty minutesEverything you need is public and none of it costs anything. Filing history, charges, director record, county court judgments, and the payment data large firms are now compelled to publish, including what they do with retention.Read it A technical drawing being marked up at a deskCommercial··5 min readQuote or estimate, and which one binds youOne is an offer that becomes a fixed price the moment it is accepted. The other is an informed guess. Almost nobody says which they are sending, and the word at the top of the page is not what decides it.Read it Tower cranes above a building under constructionHealth and safety··5 min readWhen you become the principal contractor without being toldThe duty attaches to a role, not to the size of the firm, and a second contractor arriving on site is enough to trigger it. What lands on you, and what happens when the client never appointed anybody.Read it A team working together at a shared tableChoosing software··6 min readWhat construction software actually costsThe monthly figure is the part everyone compares and the smallest part of the bill. Setup, migration, the annual uplift, and the licences you ration because they are charged per person.Read it Two colleagues at a desk after reaching an agreementTax and CIS··8 min readThe VAT reverse charge, and who accounts for the VATFive years in and it still catches firms out on every second invoice. When it applies, when it does not, the written statement that switches it off, and the wording your invoice has to carry.Read it A modern office interiorTax and CIS··7 min readReclaiming CIS deductions, and the money sitting with HMRCA limited company gets its deductions back through payroll rather than through its Corporation Tax return, and only if somebody files the right submission every month. Where the money goes, and how to stop it piling up.Read it Technical drawings and tools on a workbenchCommercial··7 min readThe gap between doing the work and having the moneyWages go out weekly, materials at thirty days, and the money comes back at sixty. Retention, CIS and the reverse charge each take a slice on the way. Why a job that made a profit can still run a firm out of cash.Read it Operatives working among steel reinforcement on a slabGetting paid··8 min readWhen the contractor above you will not payThe remedies run in a fixed order and each one costs more than the last. What to do first, what every step is worth, and the rung most disputes never get past.Read it A hand writing on documents at a deskGetting paid··8 min readPay less notices, and the timetable behind themFour dates govern every interim payment in UK construction, and statute sets them rather than goodwill. What each one is, how to work them out on your own job, and what a late notice costs the party that served it.Read it An electrician testing at a distribution boardGetting paid··6 min readPay when paid, and why it does not bind youMaking your money conditional on somebody else being paid has been ineffective in UK construction since 1998. The clause is still written into contracts, still quoted down the phone, and still works on firms that do not know.Read it Site team reviewing a risk assessment and method statement on a UK construction siteHealth and safety··7 min readRAMS that hold upWhat an inspector is actually looking for in a risk assessment and method statement, and the difference between a document that exists and one that is doing its job.Read it Retention and the money that goes missing after practical completionCommercial··6 min readRetention, and the money that goes missing after practical completionWhere cash quietly disappears between the last valuation and the release of the second half of retention, and the four dates that decide whether you ever see it.Read it Why field rollouts stall in week threeImplementation··6 min readWhy field rollouts stall in week threeMost site software is not rejected. It is quietly outlived by the paper route nobody switched off. What the firms that got it to stick did differently.Read it
WhatsApp us