Snagging, and the list
that decides when a job ends.

The difference between a snag and a defect is who pays for it. How the list gets made, why it grows after handover, and what closes it out for good.

Published ·7 min read·Written by

A snag is a small piece of work you have not finished. A defect is work you finished badly. Both appear on the same list, in the same handwriting, on the same afternoon, and the difference between them decides who pays. Almost no snagging list in the industry records which is which.

Snag or defect, and why it matters

The words get used interchangeably on site and they are not interchangeable commercially.

A snag is incomplete work. A missing socket plate, an unpainted reveal, a door that has not been adjusted. It was always yours to do, it is still yours to do, and nobody is arguing about liability.

A defect is completed work that does not comply with the contract. It might be your workmanship, it might be a material failure, it might be a design that could never have worked, and it might be damage caused after you left by another trade or by the occupier. Liability is a live question, and the answer determines whether you fix it for free.

The commercial consequence is direct. A list of two hundred items, all called snags, on which forty are damage caused by the fit-out contractor who followed you, is a list on which you have just agreed to do forty items of free work by not objecting.

The cheapest moment to challenge an item is the moment it is written down. Every day after that, challenging it looks like reluctance rather than accuracy.

What practical completion actually changes

Practical completion is not the point at which the work is perfect. On most forms it is the point at which the works are complete enough for the employer to take possession and use them, with only minor items outstanding that do not prevent that use.

Reaching it changes four things at once, which is why it is fought over:

  • Possession passes, and with it the risk of damage and the responsibility to insure.
  • Liquidated damages for delay stop running.
  • The first half of retention normally falls due.
  • The defects liability period starts.

The argument on most jobs is whether the outstanding list is small enough to be minor. There is no arithmetic for that, which is why a well-kept list with each item categorised is worth more than an argument about a total.

The defects liability period

Commonly twelve months from practical completion, six on shorter works, and twenty-four is not unusual on mechanical and electrical packages. During it you have both an obligation and a right: an obligation to return and rectify defects that are yours, and a right to be the one who does it rather than being charged for somebody else's contractor.

That right is worth protecting. If the employer engages a third party to fix something without giving you the opportunity, the cost they are entitled to recover is frequently less than the invoice they will send you, and the argument is much easier if your record shows you asked for access and were refused.

The period ends with a making good certificate, or whatever the form calls it, and on many contracts the second half of retention is due on that certificate rather than on the date. That is covered in retention and the final account, and it is where a great deal of money quietly stops moving.

What a list has to record to be useful

Most snagging lists are a location, a description and nothing else. A list that survives an argument carries more:

  1. Where, precisely. Room, level, grid or unit number. Half of all disputes about whether an item was done are disputes about which item was meant.
  2. What, described so a person who was not there can act on it.
  3. A photograph, dated. One image at the point of raising removes more argument than any amount of description.
  4. Snag or defect, stated, and if a defect, whose.
  5. Who raised it and when.
  6. Who it is assigned to, by name or by trade, not to the ether.
  7. Status, with dates. Raised, in progress, complete, verified. Complete and verified are different states and the difference is the whole point of the list.
  8. A second photograph on close-out. This is the one nearly everybody skips, and it is what turns "we did that" into evidence.

Why the list grows after handover

Every contractor has watched a list of forty items become a list of a hundred and forty over the following month, and it is rarely bad faith. Four ordinary mechanisms cause it:

The building is being used for the first time, so things that were never tested are being tested. Following trades are working in finished areas and causing damage that arrives on your list because your list is the one that exists. The employer's own inspectors are looking with a different standard from the one the contract specifies. And items get re-raised because the close-out of the first version was never recorded anywhere the second inspector could see.

Only the last of those is entirely within your control, and it is the one that a shared, dated, photographed list eliminates completely.

Closing it out

A list is closed when every item is either verified complete, agreed to be somebody else's, or formally in dispute. Items that simply stop being mentioned are not closed. They reappear at final account, usually as a deduction, usually when the person who could have explained them has left.

Get the categorisation agreed early and in writing, even informally. An email that says these thirty items we accept, these eight are damage by others, these two we consider design issues is worth more than any subsequent argument, and it costs one afternoon while the job is still live.

Where this touches the platform

Snagging in Unibuild is raised on site rather than transcribed afterwards: an item against a project and a location, with photographs taken on the phone at the moment it is raised, assigned to a person or a trade, and moved through its states with each change stamped with who made it and when. Close-out photographs sit on the same record as the raising photographs, so the before and after live together rather than in two different places. The list is visible to the office as it is built rather than at the end of the day, and where a client portal is in use the client sees the position on their own project without ringing anybody. What the platform will not do is decide whether an item is your defect or somebody else's damage. That is a commercial judgement, and the record exists so the person making it has the photograph and the date in front of them.

Where to start, on Monday

Take the last job you handed over and count how many items on its snagging list carry a photograph. Then count how many carry a close-out photograph. On most lists the first number is low and the second is nearly zero, and that gap is the reason the final account took four months.

On the next job, change one thing only: photograph every item when it is raised and again when it is done. That single habit does more for the final account than any amount of arguing later.

Sources

Checked against the source rather than against commentary. Where a schedule, a rate or a threshold is definitive on a government site, read it there.

Asked most often

The follow-up questions.

What happens to the money held back is covered in retention and the final account.

What is the difference between a snag and a defect?+
A snag is incomplete work, such as a missing socket plate or an unpainted reveal. It was always yours to finish and nobody disputes that. A defect is completed work that does not comply with the contract, and liability for it is a live question: it might be your workmanship, a material failure, a design that could never have worked, or damage caused after you left. The distinction decides who pays, and most lists never record it.
What does practical completion mean?+
The point at which the works are complete enough for the employer to take possession and use them, with only minor outstanding items that do not prevent that use. It is not perfection. Reaching it passes possession and insurance risk, stops liquidated damages running, normally triggers the first half of retention, and starts the defects liability period.
How long is the defects liability period?+
Commonly twelve months from practical completion. Six months appears on shorter works and twenty-four is not unusual on mechanical and electrical packages. During it you have an obligation to return and rectify your defects, and a right to be the one who does the work rather than being charged for somebody else's contractor.
Why does a snagging list grow after handover?+
Four ordinary reasons, and bad faith is rarely one of them. The building is being used and tested for the first time. Following trades are damaging finished areas, and your list is the one that exists. The employer's inspectors apply a different standard from the contract's. And items get raised twice because the close-out of the first version was never recorded where the second inspector could see it. Only the last is entirely within your control.
Can a client employ someone else to fix my defects?+
Usually only after giving you the opportunity to rectify. If they engage a third party without doing so, the cost they are entitled to recover is frequently less than the invoice they send, and the argument is far easier if your record shows you asked for access and were refused. Keeping that correspondence is worth more than it looks at the time.
What should a snagging list record?+
Precise location, a description somebody who was not there can act on, a dated photograph at the point of raising, whether it is a snag or a defect and whose, who raised it and when, who it is assigned to, status with dates, and a second photograph on close-out. That last one is the item nearly everybody skips, and it is what turns "we did that" into evidence.