When a job becomes notifiable,
and who tells the HSE.
Two thresholds, either of which triggers it, and a duty that sits with the client rather than with you. How to work out whether your job crosses them.
Published ·5 min read·Written by Unibuild
A project is notifiable under CDM 2015 if the construction work is scheduled to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or if it exceeds 500 person days. Either limb triggers it. The client gives the notice, on form F10, as soon as practicable before the construction phase begins.
The test, stated exactly
Regulation 6 sets two alternative thresholds, and the structure matters because it is stated wrongly in a lot of places.
- Longer than 30 working days AND more than 20 workers working simultaneously at any point on the project. Both parts of this limb have to be met. A six month job with a gang of eight never satisfies it.
- OR the work exceeds 500 person days. This limb stands alone. A short, heavily manned job can cross it without ever having 20 people on at once for 30 days.
So the connector between the two limbs is or, and the connector inside the first limb is and. Getting that the wrong way round is the commonest error, and it produces both false positives and false negatives.
Person days is simply the total of days worked by all workers on the construction phase. Ten people for fifty days is 500, which is not more than 500, so it does not cross. Ten people for fifty one days does.
Either threshold on its own is enough. Plenty of jobs are notifiable on person days while never coming close to twenty people on site at once.
Notifiable is not the same as needing a principal contractor
This is the confusion worth clearing, because the two questions get merged constantly and they have nothing to do with each other.
Needing a principal contractor turns on the number of contractors: more than one, or reasonably foreseeably more than one, and the duty attaches regardless of size or duration.
Being notifiable turns on duration and workforce size, and says nothing about how many contractors are involved.
Which produces four possible combinations, and all four occur. A small refurbishment with a builder and an electrician needs a principal contractor and is not notifiable, and that combination is extremely common. A long single-contractor job could in principle be notifiable without triggering the appointment requirement. Answer the two questions separately, in that order, and the paperwork follows. The appointment side is covered in when you become the principal contractor without being told.
Who notifies, and when
The client. Not the principal contractor, not the principal designer, and not you.
The notice must be given as soon as practicable before the construction phase begins, and it goes to the HSE, except on railway, nuclear or defence sites where it goes to the relevant authority instead.
Two practical consequences of the duty sitting with the client. First, on domestic and small commercial work the client frequently has no idea this is their job, so somebody has to tell them, and that somebody is usually you. Second, the notice is often prepared in practice by the principal contractor or principal designer on the client's behalf, which is fine, but it does not move the duty. It remains the client's.
What the notice does, and what it does not
It tells the regulator that a project of a certain size is happening, with the particulars listed in Schedule 1: the address, the client, the duty holders, the planned dates, the expected number of workers and contractors, and who is on site.
It has to be displayed in the construction site office in a comprehensible form, and updated if the particulars change materially. That display requirement is routinely forgotten, and it is one of the easiest things for an inspector to notice on arrival.
What it does not do is any of the things people fear or hope. It does not summon an inspection, it is not an application for anything, nothing has to be approved, and there is no fee. It also does not change any of your duties: a notifiable project carries exactly the same CDM obligations as a non-notifiable one of the same shape. Notification is administrative.
If it should have been notified and was not
It is a breach of regulation 6 by the client. The practical position for a contractor who realises mid-job is straightforward: raise it in writing with the client, and get it submitted. Late notification is considerably better than none, and a contemporaneous email showing you raised it is worth having if the matter is ever looked at.
The reason to bother, beyond the regulation, is that an unnotified notifiable project is an obvious signal to an inspector that the project's management arrangements were not thought about, which colours everything they look at afterwards.
Honest about the limit first: Unibuild does not submit F10 notifications and does not decide notifiability, which is a judgment about a programme. Where it helps is on the inputs and on the evidence. The thresholds are questions about duration and about how many people are on site, and a system that records who was on site each day, with clock-ins carrying a date and a job, turns person days from an estimate into an arithmetic answer. The health and safety file, phase plan, permits and site records sit against the same job, so the CDM paperwork is one record rather than a folder. What you still need is somebody who looks at the programme before the job starts and asks the question, and that is a person.
Where to start, on Monday
Take each job on your board and answer two questions, in this order. Is there more than one contractor on it, which decides the appointment. And does it cross either notification threshold, which decides the F10.
For the second, the person days arithmetic is usually the quicker route: total the days you expect each trade to be on site and add them up. Where the answer is close to 500, treat it as notifiable, because the cost of notifying a job that turned out not to need it is nothing and the cost of the reverse is not.
Then, on any job that is notified, walk into the site office and check the notice is actually displayed.
The follow-up questions.
A working list of the duties either way is in the CDM 2015 checklist.
When does a construction project need an F10 notification?+
Who submits the F10 to the HSE?+
What are 500 person days?+
Is a notifiable project the same as one needing a principal contractor?+
Does notifying a project trigger an HSE inspection?+
What if a notifiable job was never notified?+
More from Insights.
RAMS that hold upWhat an inspector is actually looking for in a risk assessment and method statement, and the difference between a document that exists and one that is doing its job.Read it →
Retention, and the money that goes missing after practical completionWhere cash quietly disappears between the last valuation and the release of the second half of retention, and the four dates that decide whether you ever see it.Read it →
Why field rollouts stall in week threeMost site software is not rejected. It is quietly outlived by the paper route nobody switched off. What the firms that got it to stick did differently.Read it →