Insight · Getting paid

Retention bonds,
and what replaces cash retention.

A retention bond swaps the money held back from every payment for a surety's promise to pay. How the JCT and NEC bonds work, what a call needs, what they cost, and where the proposed retention ban leaves them.

Published ·7 min read·Written by

Tower cranes above a building under construction

A retention bond is a guarantee from a bank or insurer that takes the place of cash retention. Nothing is held back from the contractor’s payments. Instead the surety promises to pay the employer up to the retention sum if the contractor fails to meet its obligations. With the Commercial Payments Bill proposing a ban on cash retention, the bond is one of the alternatives the government has pointed to.

What a retention bond is

The surety issues the bond to the employer who would have held retention. The contractor who would have had it deducted arranges it and pays the premium. In return, the employer agrees not to deduct retention from interim payments.

The bond has a maximum sum, set to match the retention that would otherwise have been held. On a subcontract the same arrangement runs one tier down: the subcontractor takes out the bond in favour of the main contractor.

Cash retention and a retention bond compared
PointCash retentionRetention bond
Money withheld from each paymentYes, a percentage of every valuationNone. Payments are made in full
Who holds the securityThe party above, as cash it can useA bank or insurer, as a promise to pay
Release at practical completionThe first half is paid outThe maximum sum falls by half
Release at the endThe second half is paid outThe bond expires or is released
Cost to the payeeThe use of its own money for yearsA premium, and room on its facility
If the party above failsRetention can be lost in its insolvencyNothing was held back to lose

How a retention bond is released

The JCT publishes a standard retention bond, agreed with the British Bankers’ Association, for its 2016 main contracts and subcontracts. It mirrors the two halves of cash retention.

The maximum sum stays in place until the employer tells the surety that the next interim certificate after practical completion has been issued. It then falls by half. The surety is released altogether on the earliest of three events. They are the Certificate of Making Good, payment of demands up to the maximum, and a calendar date written into the bond.

That calendar date matters. A bond that expires before the defects period ends leaves the employer unprotected, so an employer is unlikely to accept one. A bond with no realistic end date stays on the contractor’s facility for longer than the job needs.

How a call on the bond works

On the JCT form, the employer claims by written demand to the surety, with its signatures authenticated by its own bank. The demand must state the retention that would have been held at that date, and the amount claimed cannot exceed it. It must say what the money is for:

  • Costs from the contractor failing to follow the architect’s or contract administrator’s instructions, confirmed in a statement from them.
  • Insurance premiums the employer paid because the contractor did not insure the works as required.
  • Liquidated damages, with the certificate of non-completion.
  • Loss and expense after the contractor’s employment is terminated.
  • Other costs actually incurred that the contract lets the employer deduct.

The demand must also certify that the contractor was given 14 days’ written notice of the liability and did not pay. A demand that meets those requirements is conclusive evidence, for the bond’s purposes, that the amount is due. The surety pays first. Any argument about whether the employer was right comes afterwards, between employer and contractor.

A bond keeps the money with the firm that earned it. It does not keep the argument away.

On-demand and default bonds

An on-demand bond pays on a compliant demand, without the beneficiary proving a breach. A default bond, also called a conditional bond, pays only once the breach and the loss are established. The JCT form sits between them: it pays on demand, but only on a demand that ties the sum to named heads of claim and to 14 days’ notice.

For the firm taking the bond out, the wording decides the risk. A default bond with a clear expiry date carries far less exposure than a pure on-demand bond with an open end.

Retention bonds under NEC4

In the NEC4 Engineering and Construction Contract, retention is Option X16. Clause X16.3 lets the contractor give the client a retention bond, in the form set out in the Scope, in place of retention. The contract states one reason for refusing it: a provider whose commercial position is not strong enough. Refusing it for a reason the contract does not state is a compensation event.

What a retention bond costs

There is no published rate. The premium depends mainly on the contractor’s financial standing, so smaller firms pay more for the same cover. Research for the government by Pye Tait in 2017 found premiums of 1% to 10% of the bond value, with a minimum of around £750.

The Bill’s impact assessment assumed premiums of 3% of the retention sum for small firms, 1.8% for medium firms and 0.8% for large ones. It called these weak assumptions, because the market is small and evidence limited.

The premium is not the only cost. A bank that issues a bond normally sets the bonded amount against the firm’s borrowing facility. Banks and insurers both take a counter-indemnity. Either way, a bond protects the employer rather than the firm that takes it out: after paying a claim, the surety recovers the money from the contractor.

How often bonds are used

Rarely, so far. Pye Tait found retention bonds in place of cash on under 0.2% of clients’ contracts and 1% of contractors’ contracts. Clients and main contractors prefer cash, which they can use as working capital, and many treat a claim on a bond as slower than deducting from a payment.

The same research found why the government wants a change. 44% of contractors who had retention held in the previous three years had lost some to an insolvency further up the chain. Cash retention sits on the balance sheet of the firm above, and goes with it if that firm fails.

Does the retention ban cover retention bonds?

The ban in the Commercial Payments Bill is aimed at money: a party deducting or keeping back a percentage of what is due, until a condition for release is met. A retention bond involves no deduction. The Bill does not mention bonds, and nothing in it bans them.

Ministers have pointed to bonds as the replacement. At Report in the Lords on 15 September 2026, the government said it favours alternative forms of surety, such as performance, retention and warranty bonds. It will work with surety providers so that alternatives are available when the ban comes into force. It added that money held by a third party as security could itself amount to a retention. Ministers also keep a power to amend the definitions by regulations.

The impact assessment chose the ban over a framework that would have protected cash retention in trust, mainly on cost. Under the ban, employers can ask for a bond or other surety, but nothing requires one. The Commercial Payments Bill and the retention ban sets out the timeline.

What it means for a subcontractor

During the two-year transition, expect bond requests to grow as main contractors look for security that survives the ban. Four checks are worth making before agreeing to one:

  • The type. A default bond, or the JCT form with its named heads of claim, rather than a pure on-demand bond.
  • The maximum sum and the reduction. It should match the retention it replaces and fall by half at practical completion.
  • The expiry date. Set against the end of the defects period, with nothing open-ended.
  • The facility. What the bond takes out of the firm’s borrowing capacity, for how long, across every job carrying one.
Where this touches the platform

In Unibuild, retention a client withholds is recorded against each payment it came off, so the balance held on every job is a running figure in the aged debt. Where a bond replaces cash, it is held against the job with its maximum sum, its reduction at practical completion and its expiry date. The dates are watched rather than remembered. On subcontract orders, the retention percentage or the bond required is a structured field printed on page one.

Bond wording varies, and the JCT and NEC forms are amended on many projects. This article follows the JCT Retention Bond 2016 and NEC4 Option X16 as published, and the Commercial Payments Bill as passed by the House of Lords on 20 October 2026. It is general guidance rather than legal advice.

Asked most often

The follow-up questions.

What the proposed ban does to cash retention, and when, is in the Commercial Payments Bill and the retention ban.

What is a retention bond in construction?
A guarantee from a bank or insurer given in place of cash retention. The employer agrees not to deduct retention from payments, and the surety promises to pay the employer up to the retention sum if the contractor fails to meet its obligations.
Who pays for a retention bond?
Normally the contractor or subcontractor, because it takes the bond out in favour of the party above. In return it is paid in full, with nothing held back from each valuation.
How much does a retention bond cost?
It depends mainly on the firm’s financial standing. Research for the government in 2017 found premiums of 1% to 10% of the bond value, with a minimum of around £750. The Bill’s impact assessment assumed 3% of the retention sum for small firms and 0.8% for large ones.
When is a retention bond released?
On the JCT form, the maximum sum falls by half after the next interim certificate following practical completion. The surety is released at the Certificate of Making Good, on payment up to the maximum, or on the calendar date in the bond, whichever comes first.
Can an employer call a retention bond without proving a breach?
On an on-demand bond, yes. On the JCT form the demand must name the heads of claim and certify 14 days’ written notice to the contractor. A compliant demand is then conclusive evidence for the bond’s purposes. A default bond pays only once the breach is established.
Will retention bonds be banned with retention?
Not under the Bill as drafted. The Commercial Payments Bill bans money being deducted or kept back, and a bond involves no deduction. The government has said it favours alternative forms of surety, including retention bonds, and will work with surety providers so they are available when the ban starts.
Does a retention bond affect my bank facility?
A bond from your bank normally counts against your borrowing facility for as long as it runs. Banks and insurers both take a counter-indemnity. Either way, if the bond is called, the surety recovers what it paid from you.
Does NEC4 allow a retention bond?
Yes. Under Option X16, clause X16.3 lets the contractor give a retention bond in place of retention. The contract states one reason for refusing it, a provider whose commercial position is not strong enough. Refusing it for a reason the contract does not state is a compensation event.
Does Unibuild track retention bonds?
Yes. A bond is held against the job with its maximum sum, its reduction at practical completion and its expiry date, and the dates are watched with reminders. Cash retention withheld is a running figure per job in the aged debt. See applications for payment.
Get a quote
One figure per firm · For UK firms

Right, let’s talk numbers.

Five things about your business. We work your fee out properly and put it in writing the same working day.

What we build for you

  • Your own portalIn the browser, built around your firm
  • Your own appiOS and Android, under your name
  • Everyday AI includedHeavier AI at cost, nothing added
  • One platformEverything in one place, set up by us

Would you rather see it running first? Book a 30-minute demo

Quotation request