Retention bonds,
and what replaces cash retention.
A retention bond swaps the money held back from every payment for a surety's promise to pay. How the JCT and NEC bonds work, what a call needs, what they cost, and where the proposed retention ban leaves them.
Published ·7 min read·Written by Darshan Parmar, Founder

A retention bond is a guarantee from a bank or insurer that takes the place of cash retention. Nothing is held back from the contractor’s payments. Instead the surety promises to pay the employer up to the retention sum if the contractor fails to meet its obligations. With the Commercial Payments Bill proposing a ban on cash retention, the bond is one of the alternatives the government has pointed to.
What a retention bond is
The surety issues the bond to the employer who would have held retention. The contractor who would have had it deducted arranges it and pays the premium. In return, the employer agrees not to deduct retention from interim payments.
The bond has a maximum sum, set to match the retention that would otherwise have been held. On a subcontract the same arrangement runs one tier down: the subcontractor takes out the bond in favour of the main contractor.
| Point | Cash retention | Retention bond |
|---|---|---|
| Money withheld from each payment | Yes, a percentage of every valuation | None. Payments are made in full |
| Who holds the security | The party above, as cash it can use | A bank or insurer, as a promise to pay |
| Release at practical completion | The first half is paid out | The maximum sum falls by half |
| Release at the end | The second half is paid out | The bond expires or is released |
| Cost to the payee | The use of its own money for years | A premium, and room on its facility |
| If the party above fails | Retention can be lost in its insolvency | Nothing was held back to lose |
How a retention bond is released
The JCT publishes a standard retention bond, agreed with the British Bankers’ Association, for its 2016 main contracts and subcontracts. It mirrors the two halves of cash retention.
The maximum sum stays in place until the employer tells the surety that the next interim certificate after practical completion has been issued. It then falls by half. The surety is released altogether on the earliest of three events. They are the Certificate of Making Good, payment of demands up to the maximum, and a calendar date written into the bond.
That calendar date matters. A bond that expires before the defects period ends leaves the employer unprotected, so an employer is unlikely to accept one. A bond with no realistic end date stays on the contractor’s facility for longer than the job needs.
How a call on the bond works
On the JCT form, the employer claims by written demand to the surety, with its signatures authenticated by its own bank. The demand must state the retention that would have been held at that date, and the amount claimed cannot exceed it. It must say what the money is for:
- Costs from the contractor failing to follow the architect’s or contract administrator’s instructions, confirmed in a statement from them.
- Insurance premiums the employer paid because the contractor did not insure the works as required.
- Liquidated damages, with the certificate of non-completion.
- Loss and expense after the contractor’s employment is terminated.
- Other costs actually incurred that the contract lets the employer deduct.
The demand must also certify that the contractor was given 14 days’ written notice of the liability and did not pay. A demand that meets those requirements is conclusive evidence, for the bond’s purposes, that the amount is due. The surety pays first. Any argument about whether the employer was right comes afterwards, between employer and contractor.
A bond keeps the money with the firm that earned it. It does not keep the argument away.
On-demand and default bonds
An on-demand bond pays on a compliant demand, without the beneficiary proving a breach. A default bond, also called a conditional bond, pays only once the breach and the loss are established. The JCT form sits between them: it pays on demand, but only on a demand that ties the sum to named heads of claim and to 14 days’ notice.
For the firm taking the bond out, the wording decides the risk. A default bond with a clear expiry date carries far less exposure than a pure on-demand bond with an open end.
Retention bonds under NEC4
In the NEC4 Engineering and Construction Contract, retention is Option X16. Clause X16.3 lets the contractor give the client a retention bond, in the form set out in the Scope, in place of retention. The contract states one reason for refusing it: a provider whose commercial position is not strong enough. Refusing it for a reason the contract does not state is a compensation event.
What a retention bond costs
There is no published rate. The premium depends mainly on the contractor’s financial standing, so smaller firms pay more for the same cover. Research for the government by Pye Tait in 2017 found premiums of 1% to 10% of the bond value, with a minimum of around £750.
The Bill’s impact assessment assumed premiums of 3% of the retention sum for small firms, 1.8% for medium firms and 0.8% for large ones. It called these weak assumptions, because the market is small and evidence limited.
The premium is not the only cost. A bank that issues a bond normally sets the bonded amount against the firm’s borrowing facility. Banks and insurers both take a counter-indemnity. Either way, a bond protects the employer rather than the firm that takes it out: after paying a claim, the surety recovers the money from the contractor.
How often bonds are used
Rarely, so far. Pye Tait found retention bonds in place of cash on under 0.2% of clients’ contracts and 1% of contractors’ contracts. Clients and main contractors prefer cash, which they can use as working capital, and many treat a claim on a bond as slower than deducting from a payment.
The same research found why the government wants a change. 44% of contractors who had retention held in the previous three years had lost some to an insolvency further up the chain. Cash retention sits on the balance sheet of the firm above, and goes with it if that firm fails.
Does the retention ban cover retention bonds?
The ban in the Commercial Payments Bill is aimed at money: a party deducting or keeping back a percentage of what is due, until a condition for release is met. A retention bond involves no deduction. The Bill does not mention bonds, and nothing in it bans them.
Ministers have pointed to bonds as the replacement. At Report in the Lords on 15 September 2026, the government said it favours alternative forms of surety, such as performance, retention and warranty bonds. It will work with surety providers so that alternatives are available when the ban comes into force. It added that money held by a third party as security could itself amount to a retention. Ministers also keep a power to amend the definitions by regulations.
The impact assessment chose the ban over a framework that would have protected cash retention in trust, mainly on cost. Under the ban, employers can ask for a bond or other surety, but nothing requires one. The Commercial Payments Bill and the retention ban sets out the timeline.
What it means for a subcontractor
During the two-year transition, expect bond requests to grow as main contractors look for security that survives the ban. Four checks are worth making before agreeing to one:
- The type. A default bond, or the JCT form with its named heads of claim, rather than a pure on-demand bond.
- The maximum sum and the reduction. It should match the retention it replaces and fall by half at practical completion.
- The expiry date. Set against the end of the defects period, with nothing open-ended.
- The facility. What the bond takes out of the firm’s borrowing capacity, for how long, across every job carrying one.
In Unibuild, retention a client withholds is recorded against each payment it came off, so the balance held on every job is a running figure in the aged debt. Where a bond replaces cash, it is held against the job with its maximum sum, its reduction at practical completion and its expiry date. The dates are watched rather than remembered. On subcontract orders, the retention percentage or the bond required is a structured field printed on page one.
Bond wording varies, and the JCT and NEC forms are amended on many projects. This article follows the JCT Retention Bond 2016 and NEC4 Option X16 as published, and the Commercial Payments Bill as passed by the House of Lords on 20 October 2026. It is general guidance rather than legal advice.
Sources
Checked against the source rather than against commentary. Where a schedule, a rate or a threshold is definitive on a government site, read it there.
- JCT Retention Bonds 2016, agreed with the British Bankers' Association jctltd.co.uk
- NEC and Construction Leadership Council: retentions webinar, Option X16 neccontract.com
- Pye Tait Consulting for BEIS: Retention Payments in the Construction Industry (2017) assets.publishing.service.gov.uk
- GOV.UK: Retention payments in the construction industry, consultation GOV.UK
- Commercial Payments Bill: final stage impact assessment, Department for Business and Trade bills.parliament.uk
- Hansard: Commercial Payments Bill [HL], Lords Report, 15 September 2026 hansard.parliament.uk
- Hansard: Commercial Payments Bill [HL], Lords Committee, 21 July 2026 hansard.parliament.uk
- NSCC: Using a retention bond nscc.org.uk
The follow-up questions.
What the proposed ban does to cash retention, and when, is in the Commercial Payments Bill and the retention ban.
What is a retention bond in construction?
Who pays for a retention bond?
How much does a retention bond cost?
When is a retention bond released?
Can an employer call a retention bond without proving a breach?
Will retention bonds be banned with retention?
Does a retention bond affect my bank facility?
Does NEC4 allow a retention bond?
Does Unibuild track retention bonds?
More from Insights.
The Commercial Payments Bill, and the end of cash retentionThe Bill passed the House of Lords on 20 October 2026. It would ban retention in construction contracts after a two-year transition, cap the final date for payment at 60 days and stop contracts writing statutory interest out. What changes, for which contracts, and when.Read it →
Retention, and the money that goes missing after practical completionWhere cash quietly disappears between the last valuation and the release of the second half of retention, and the four dates that decide whether you ever see it.Read it →
Credit checking the firm above you, free, in twenty minutesEverything you need is public and none of it costs anything. Filing history, charges, director record, county court judgments, and the payment data large firms must publish.Read it →All 12 articles on getting paid.